Title | CIVE1151 Lect 3 eqivalent load |
---|---|
Course | Concrete Structures 2 |
Institution | Royal Melbourne Institute of Technology |
Pages | 17 |
File Size | 1 MB |
File Type | |
Total Downloads | 153 |
Total Views | 512 |
Equivalent Load Concept in Prestressed Concrete • Week 3 Flexure in beams with prestress Chapter 6 text Warner et al. Equivalent load method can be used to evaluate the effects of prestress. This approach provides the basis for a design technique called load balancing, which is useful in the prelimi...
Equivalent Load Concept in Prestressed Concrete • Week 3 Flexure in beams with prestress Chapter 6 text Warner et al.
Equivalent load method can be used to evaluate the effects of prestress. This approach provides the basis for a design technique called load balancing, which is useful in the preliminary design of prestressed concrete structures.
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Forces at Anchorages At its anchorage a prestressing cable exerts on the concrete an equivalent load whose magnitude is that of the prestressing force and whose direction is that of the cable at the anchorage
P
P
Psin Pcos
Equivalent load
P
components
P
For small angles
M=Pe
e
P
e P
equivalent load – eccentric anchorage RMIT University©
components
Lecture Notes prepared by Dr Rebecca Gravina
Equivalent system at centroidral axis
Draped Cables • Pretensioned beams – Tendons are either straight or connected by kinks as below
P
θ
e0
L/3
L/3
Angle at the ends of the cables θ= 3eo/L (assuming for small angles tan θ = θ) Forces applied at each end of beam consist of horizontal component P and vertical component P At a kink, concrete needs to apply a vertical force F = 3Peo/L to balance the cable forces. RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Equivalent Loads from a draped cable after prestress 3Peo/L
3Peo/L P
P 3Peo/L
3Peo/L
Moment in mid-span from prestress = -3Peo/L x L/3 = -Peo This moment is same as that we used earlier in section analysis ie Mp=Peo , however, this concept has some advantages in selecting a prestress force
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Forces in curved cables Δθ = curvature x Δx ΔF=2Psin(Δθ/2) = P Δθ ΔF
ΔF/ Δx = P Δθ/Δx = Pk
P
Where k = curvature (change in P
slope per unit length)
Δx
Δθ = kx
ΔF
P
Force triangle
P
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Parabolic cables x h
y L
Equation for the parabola can be established based on a generic expression: y=ax2+bx+c and Boundary conditions, x=0, y=0 and x=L/2, y=h y = 4h[x/L-(x/L)2] Slope= dy/dx=θ=4h/L[1-2(x/L)] Curvature k = d2y/dx2 = -8h/L2 Force per unit length = wp = Pk = -8Ph/L2 wp is a uniformly distributed upward force exerted on the beam due to prestress RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Equivalent load –Parabolic cable
P P
P P
wp L wp= 8Ph/L2
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Worked example- Calculation of stresses using the equivalent load method ex 6.2 text A prestressed concrete beam spans 10 m and has a rectangular cross section 800 mm deep and 400 mm wide. It is post-tensioned by a cable having a cross-sectional area of 1000 mm2. The cable eccentricity varies parabolically from zero at each end to a maximum of 250 mm at midspan, where the prestressing force is 1200 kN. f’c = 32 MPa Determine •
The stresses at mid-span due to prestress acting alone
•
The stress at midspan due to prestress, self weight and a 30 kN/m load
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Calculation of stresses using the equivalent load method P
h=250mm
P
wp =24kN/m
P=1200kN
P=1200kN
L P = 1200kN, = 4h/L = (4 x 0.25)/10 = 0.1 rad Downward force at each anchorage: P = 0.1 x 1200 = 120kN Udl due to prestress: wp= 8Ph/L2 = (8 x 1200 x 0.25)/ 102 = 24kN/m The stress resultants at mid-span due to equivalent loads are: Bending moment M = -(120 x 5) +(24 x 5 x 2.5) = -300kNm Axial Force N = 1200kN (Compression) The extreme fibre stresses due to prestress are therefore:
tp
P Pe 1200x10 3 1200x103 x 250x 200 3.75 7.03 3.28 MPa( tension) yt Ag I g 320,000 17.07 x10 9
bp
P Pe yt 3.75 7.03 10.78 MPa(compression) Ag I g
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
The extreme fibre stresses due to prestress, self weight and live load: To determine conditions under the full load, we add the applied loads, 30 +8 = 38kN/m to the equivalent upward load of 24kN/m exerted by the prestressing cable. That is: Net load can be calculated as: Self weight = 8kN/m Live load = 30kN/m Prestress equivalent load =wp =24kN/m Net load = 8+30-24=14kN/m At mid–span the bending moment is M = wl2/8 = (14 x 102)/8=175kNm
My 175x106 x 400 4.1MPa I 17.07 x109 t due to applied BM 4.1MPa b due to applied BM 4.1MPa
stresses due to applied BM
As before, the uniform compressive stress due to the axial prestress is 3.75MPa so that the total extreme fibre stresses are : t 3.75 4.1MPa 7.85 MPa(compression) b 3.75 4.1MPa 0.35MPa(tension)
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Load Balancing Determining the equivalent upward load due to prestress can be useful to determine the required prestress force to balance a given set of applied loads.
24kN/m
120kN 1200kN
120kN 1200kN
24kN/m
Two equal and opposite load systems acting on concrete 1200kN
1200kN
24kN/m
120kN
120kN Cable shown as freebody
Load balancing; internal equivalent loads are equal and opposite to a system of externally applied design loads RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Prestressing Force • Up to this point we have simply used prestressing force, P as constant throughout length of beam. • In reality, loss of prestress force in tendon occurs immediately after tendons are stressed and continue to occur throughout the life of prestressed member • In week 5 you will be shown how to calculate loss of prestress at different stages, namely – Immediate loss – occurs immediately after transfer (includes friction loss) – Deferred loss - Time-dependent takes place gradually over time • Load balancing calculations are based on effective prestress, Pe after all losses have occurred. • Calculations of conditions immediately after transfer are based on initial prestress force, Pi
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Pj
Pj
Jacking Pj
RMIT University©
Transfer Immediate losses
Pi
End of design life Deferred losses
Lecture Notes prepared by Dr Rebecca Gravina
Pe
Worked example- Calculation of stresses using the equivalent load method ex 6.3 text
• A post-tensioned one-way slab is 300 mm thick and is required to support a superimposed load of 12kPa over a simply supported span of 10 m. Determine the prestress details to keep the slab level under a superimposed live load of 4 kPa. Also determine the load which will cause decompression of the bottom fibre of the beam. • Assume that the deferred losses of prestress is 18% and the friction loss at mid-span is 5%.
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
Prestress force required to balance the self-weight. • Load to be balanced = self-weight. • Consider 1 m width of the slab and treat it as a beam.
300mm
30 + 16mm=46mm
With properties Area = Ag = 300,000mm2/m Second moment of area = Ig = 1000x3003/12 Self-weight = 0.3x1x25=7.5kPa Load to be balanced (ie Upward UDL required from prestress) = 7.5+4.0 = 11.5kPa The cable eccentricity = (300/2)- 46=104mm
wp
8 Pe L2 wp L2
11.5 102 Pe 1382 kN / m 8e 8 0.104 This is the prestress force requried during service - after all prestress losses have occured Pe RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
• Since time dependent losses in this case reduce the initial value of the prestressing force by 18% the required initial prestressing force at mid-span is 1382 1685 kN / m 0.82 • The initial prestressing force at the anchorage, allowing for 5 % losses due to friction is: Pi
Pj
1685 1775kN / m 0.95
• A four strand cable containing 12.7mm super grade strands (minimum breaking load per 12.7mm strand is 184kN from table 3.3.1 of As3600-2009) stressed to 75 per cent of the minimum breaking stress provides an initial force of 522kN (=0.75*184*4). The required spacing is
1000 x 522 294, ie use 300mm 1775
RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina
A Quick check to ascertain whether the beam can sustain stresses induced at transfer under the selected prestress force • AS3600 requires a rigorous calculation based on limit state design philosophy to check whether the beam is safe under the stresses induced at transfer. However, a simple stress check can usually be performed after selection of the prestress force to ensure that the beam will not fail at transfer. • Clause 8.1.6.2 Prestressed beam at transfer – The maximum compressive stress in the concrete, under the loads at transfer is not to exceed 0.5fcp • Clause 8.6.2 Crack control for flexure in prestressed beams at transfer and under service loads – Flexural cracking controlled if maximum tensile strength in the concrete does not exceed 0.25√f’c (Fully prestressed beam) – if this stress is exceeded need to provide steel reinforcement and limit the maximum flexural tensile stress under short-term service loads to 0.6√f’c (Partially prestressed beam) • This process establishes the upper limit of the jacking force allowed in a section. However, the design check at transfer still needs to be performed as per AS3600 requirement. RMIT University©
Lecture Notes prepared by Dr Rebecca Gravina...