Title | Frustration 17 |
---|---|
Course | Law of Contract |
Institution | University of Birmingham |
Pages | 2 |
File Size | 65.6 KB |
File Type | |
Total Downloads | 92 |
Total Views | 128 |
frustration...
Frustration – Taylor v Caldwell Cf Jackson v Union Marine Insurance Co Ltd In November 1871, the claimant owner of a ship entered into a charter party with a third party charterer. The ship was required to proceed with ‘all possible dispatch’ from Liverpool to Newport, and there to load a cargo (iron nails) for carriage to San Francisco. The ship sailed on 2 January 1872, but already on her way to Newport she ran aground. The ship was not fully repaired until the end of August. In the meantime, on 15 February, the charterers had given up on the charter and chartered another ship.
The claimant shipowner brought an action against its insurer (the defendant) for loss of freight.
The claimant was entitled to recover under the insurance if the freight was lost by a ‘peril of the sea’ but not if it was lost for breach of contract.
Legal impossibility/ subsequent illegality… usually dealing with the outbreak of war. Met Water board v Dick Kerr Co Ltd. [1918] HOL The claimant water board concluded a contract with D contractors for the purposes of building a reservoir The reservoir was to be constructed in 6 years, commencing July 1914. On 21 February 1916, the Ministry of Munitions exercised its wartime powers to prevent work on the contract continuing, and to disperse and sell the plant as directed by the Ministry. The claimant sought a declaration that the contract was still continuing. Held: The performance of the contract had become illegal. Since the illegality and the delay consequent on it were indefinite, the contract had ceased to be binding. (There was a clause – condition 32 – expressly dealing with delay caused by difficulties, but it did not cover delay of the kind on question). Krell v Henry The defendant saw an announcement in the windows of the claimant’s flat in Pall Mall. According to this announcement the claimant was willing to hire out his flat on the days of the coronation procession, namely 26 and 27 June. The defendant hired the flat for the two days (but not the nights). The written contract did not mention the procession. Unfortunately, early in the morning of 24 June, the procession was cancelled due to the King’s illness.
The defendant refused to pay the remaining balance of £50 and the claimant brought an action to recover it. Held: The principle of Taylor v Caldwell applied so that the £50 did not have to be paid.
Factors excluding frustration
Self induced frustration 2. Express provision 3. Foreseeable events 1.
*law reform for frustrated contracts Economic analysis of the law ...