Lessons Learned Document Project Name:
ABC Software Application Upgrade
Prepared by:
John Doe
Date (MM/DD/YYYY):
09/17/07
The purpose of this document is to help the project team share knowledge gained from experience so that the entire organization may benefit. A successful Lessons-Learned program will help project teams:
Repeat desirable outcomes Avoid undesirable outcomes
1. Project Close-Out Discussion A. List of project’s biggest successes Description Windows support on time and responsive to all internally escalated issues Vendor support outstanding
Factors that Promoted this Success Staggered shifts, positive attitude and team willingness to do whatever it takes to succeed Vendor on-site support provided, good vendor-client relationship
Desktop & App Support on go-live on time and responsive to user issues
Staggered shifts, positive attitude and team willingness to do whatever it takes to succeed
Unix support on time and responsive
Team willingness to do whatever it takes to succeed
PM support and coordination outstanding and always present
Presence of PM ensured that the team was focused and could channel all issues/concerns
50% of ABC Software Application failures addressed on first point of contact
Extra support and IT team staff available post-upgrade to address any issues
Upgrade process for ABC Software Application Database went quickly and smoothly.
Upgrade process replicated prior to actual production upgrade
B. List of project’s biggest failures Description
Net Effect on Project
ABC Software Application deployment had 30% of all workstations listed as non-responsive
Number of ABC Software Application cases on post-upgrade Monday reached 38. Additional support staff needed to handle extra load.
Customer announcements inconsistent
Customers unaware of upgrade and or of application availability
VPN access unavailable post-upgrade
Remote Access to Application unavailable
Deviation from pre-upgrade
Additional time and resources used to address issues Page 1 of 3
1. Project Close-Out Discussion preparation plan. Domain Name Services changes not verified successfully.
Additional time and resources used to address issues. Remote connectivity to application unavailable.
Executive and Senior Management not available during late night hours
High-level decisions could not be made
C. List areas of potential improvement: Description
Possible Mitigation
Domain Name Services not updated immediately on some desktops post Domain Name Services change
Domain Name Services Resetting on Desktops
Did not take advantage of vendor support during free moments, especially post-upgrade
Dedicate resource to work on issues post-upgrade
No secondary Unix resource available to assist primary resource
Provide secondary Unix resource
Coordination with Hospital-IT must happen during early stages of the planning process
Reach out to Hospital-IT earlier
Developers begin code migration/routines testing directly after upgrade and thin client testing deemed successful to cut down on application downtime
Request IT resources to be available earlier to begin workflow testing
Code freeze miscommunication.
Sign-off from not only IT Manager, but also resources
Internal communication breakdowns occurred between ITS groups.
Ground rules that all issues/concerns/request need to be communicated to PM
Issue Tracking different per group
Need centralized issue tracking system
D. Enter other comments: Overall IT team deemed the project a success.
Page 2 of 3
3. Project Lessons-Learned Document / Signatures Project Manager:
John Doe
I have reviewed the information contained in this Project Lessons-Learned Document and agree: Name
Title
Signature
Date (MM/DD/YYYY)
The signatures above indicate an understanding of the purpose and content of this document by those signing it. By signing this document, they agree to this as the formal Project Lessons-Learned Document.