Title | Method statement of waterway tunnels concrete lining. |
---|---|
Author | naveed Abbasi |
Pages | 95 |
File Size | 7.1 MB |
File Type | |
Total Downloads | 756 |
Total Views | 928 |
Method statement of waterway tunnels concrete lining. Owner’s Engineer Doc. No DLJV-CONS-MS-WT-02 Rev 03 Method Statement for Waterway tunnels lining concrete Project Name : Gulpur Hydropower Project Client : Mira power Limited Consultant : MWH NESPAK JV Contractor : Daelim-Lotte JV Site : Gulpur 03...
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Owner’s Engineer 03
Rev
Method Statement for Waterway tunnels lining concrete
Project Name
:
Gulpur Hydropower Project
Client
:
Mira power Limited
Consultant
:
MWH NESPAK JV
Contractor
:
Daelim-Lotte JV
:
Gulpur
Site
03 07/06/2017 Issued for Approval
Naveed
Naseem
Tanzeel
Javed Afzal Lee Jae Chul Cho Sang wan
02 23/04/2017 Issued for Approval
Naveed
Naseem
Tanzeel
Javed Afzal Lee Jae Chul Cho Sang wan
01 26/03/2017 Issued for Approval
Naveed
Naseem
Tanzeel
Javed Afzal Lee Jae Chul Cho Sang wan
00 18/01/2017 Issued for Approval
Naveed
Naseem
Tanzeel
Javed Afzal Lee Jae Chul Cho Sang wan
Rev.
Date
Description
Prepared by QA/QC
EHS
Const.
Approved by
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Owner’s Engineer 03
Contents 1. Purpose……………………………………………………………………………….3 2. Scope of work…………………………………………………………………………3
3 Organizatio and responsibilitie ……………………………………………………...9 4. Resources……………………………………………………………………………12 5. Execuation flow diagrame …………………………………………………………..14 6. Execution procedure………………………………………………………………….16 7. Quality assurance and Quality controll Plan………………………………………...26 8. Health, Safety and Environment management plan……………………………….....32 9. Attachments…………………………………………………………………………..44
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Owner’s Engineer 03
1. Purpose This Method Statement covers the construction works of waterway tunnels concrete lining. The main purpose of this method Statement is:
•
To outline the works involved in this particular Structure.
•
To provide a document that managers must read and understand before starting the job.
•
To meet legal requirements, that is, hazard identification and control.
•
To program work, materials, time, staff, and to anticipate possible problems;
•
To use as a tool in quality assurance.
2. Scope of work. 2.1 Introduction of Headrace tunnel Headrace tunnels are water way pressure tunnels which composed Vertical pressure shaft, lower bend Horizontal pressure tunnel, penstock and outlet {Figure 1: waterway tunnels plan}
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Each waterway tunnel contains: a) A vertical pressure shaft of 44.5 m height and 6.7m inner diameter (after lining concrete) b) A horizontal pressure tunnel of 122.5 m length with 6.7 inner diameter after lining.
{Figure 2: waterway tunnels 3D profile}
Vertical pressure tunnel H=44.5, D=6.7(inner)
2.1
Horizontal pressure tunnel L=122.5, D=6.7(inner)
Owner’s Engineer 03
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
2.2 Design and Specification Each vertical shaft contains: a) A vertical pressure shaft of 24.5 m height with 6.7m inner diameter(after lining concrete) b) A vertical transition part of 10.5 m height with 6.7m inner diameter(after lining concrete) Each horizontal tunnel contains: a) A lower bend of 19.635 m length with 6.7m inner diameter (after lining concrete). b) A horizontal pressure tunnel of 50.650 length with 6.7 inner diameter after lining concrete. c) A Steel penstock tunnel of 55 m length with 6.7 inner diameter after steel lining
{Figure 3: Waterway Tunnels profile}
Owner’s Engineer 03
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Both Headrace tunnels has exactly the same length, diameter and design. {Figure 4: Vertical pressure Tunnel} Specification
Shape
circular
Diameter
7.6m (Inner Circular)
Height
24.5 m
Type of lining
Concrete lining
Thickness of lining
400 mm
Location
Typical cross section
Vertical Shaft tunnel 1 & 2
Items
{Figure 5: Vertical Tunnel transition part} Specification
shape
Square
Size
7.6×7.6m Inner After lining
height
10.5 m
Type of lining
Concrete lining
Thickness of lining concrete
1000 mm
Location
Horizontal Tunnel 1 & 2
Items
Typical cross section
Owner’s Engineer 03
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
{Figure 6: Lower bend} Specification
Shape
circular
Diameter
7.6m Inner (after lining)
length
19.635 m
Type of lining
Concrete lining
Thickness of lining concrete
1000 mm
Location
Typical cross section
Lower bend 1 & 2
Items
{Figure 7: Horizontal pressure Tunnel} Specification
Shape
Horse shoe
Diameter
7.6m (Inner Circular)
length
50.650 m
Type of lining
Concrete lining
Thickness of lining concrete
400
Location
Horizontal pressure Tunnel 1 & 2
Items
Typical cross section
Owner’s Engineer 03
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Owner’s Engineer 03
{Figure 8: steel penstock Tunnel}
Type
Horse shoe
Diameter
7.6m (Inner Circular)
length
55 m
Type of lining
Steel lining
Thickness of lining concrete
700~1000 mm
Location
Typical cross section
Including out let part
Specification
Steel penstock Tunnel 1 & 2
Items
2.3 Work scope. The scope of works covers work procedures and technical requirements for cleaning, leveling concrete, steel fixing, fixing of formwork, pouring of concrete, curing of concrete, and to maintain quality and ensure structures are built in conformance with the design alignment.
2.4 Reference Documents. 2.4.1
Drawings(Revision-C)
1. GPDD-C-WT-001---------------------------------------------------------Water way General Plan 2. GPDD-C-WT-001------------------------------------------------Water way Profile (Tunnel No.1) 3. GPDD-C-WT-001------------------------------------------------Water way Profile (Tunnel No.2) 4. GPDD-C-IPTP-CLR-001------Inlet portal Transition part concrete lining reinforcement 1/3) 5. GPDD-C-IPTP-CLR-002------Inlet portal Transition part concrete lining reinforcement 2/3) 6. GPDD-C-IPTP-CLR-003------Inlet portal Transition part concrete lining reinforcement 3/3) 7. GPDD-C-VPT-CLR-001---------Vertical pressure tunnel concrete lining reinforcement 1/3)
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Owner’s Engineer 03
8. GPDD-C-IPTP-CLR-002-------- Vertical pressure tunnel concrete lining reinforcement 2/3) 9. GPDD-C-IPTP-CLR-003-------- Vertical pressure tunnel concrete lining reinforcement 3/3) 9. GPDD-C-VPT-0001------------------Vertical pressure tunnel Excavation cross sections (1/2) 10. GPDD-C-LB--LBP-0001-----------------------Lower Bend Profile and typical sections (1/2) 11. GPDD-C-LB--LBP-0002------------------------Lower bend profile and typical sections (2/2) 12. GPDD-C-LB-CLR -0001--------------------Lower bend concrete lining reinforcement (1/2) 13. GPDD-C-LB-CLR-0002---------------------Lower bend concrete lining reinforcement (2/2) 14. GPDD-C-HPT-TS-0001--------------------------Horizontal pressure tunnel typical sections 15. GPDD-C-HPT-ESC-0002-------Horizontal pressure tunnel concrete lining reinforcement 16. GPDD-C-SPT-TS-0001---------------------------------Steel penstock tunnel typical sections 17. GPDD-C-OPT-ETS-0001----------------Outlet pressure tunnel typical excavation sections
2.4.2
Specifications(Revision-C)
1. Tunnels.
3. Organization and responsibilities Site Manager:
Cho Sung wan
• Summing up the result of management review of each discipline and reporting the results to project Manager.
• Planning and controlling project schedule. • Checking, analyzing and reporting the differences between schedule and actual progress. • Coordination to each section with respect to relevant technical matters. • Supervising the operation of document control system. • Controlling the project’s design documents and the change of the design documents at site. • Controlling for expediting the delivery of purchased material and handling materials at site.
Construction Manager: Mr. Lee Jae Chul • Ensuring identification and analysis of the technical requirements of the project. • Assuring that organization is equipped with adequate resources and information to achieve quality. • Assisting the Site manager in any aspect regarding engineering matter. • Practical responsibilities for implementation of work execution • Control of manpower and equipment • Coordination with QA/QC department regarding inspection and testing • Check and review of progress as per schedule
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Site engineer:
Rev
Mr. Naveed Akhtar
•
Preparation of work procedures
•
Document and drawing control.
•
Coordination with QA/QC department regarding inspection and testing
•
Check and review of progress schedule.
•
Control of manpower and equipment
•
Coordination with design and planning department
•
Assisting the Construction manager in any aspect regarding engineering matter.
QC Manager
Owner’s Engineer 03
Mr. Naseem
•
Initializing and establishing the quality management system through project QA/QC plan
•
Having responsibility to assure that all project activities affecting quality are in compliance with this plan.
•
Establishing objectives of continual improvement.
•
Ensuring surveillance, evaluation and inspection of materials.
•
Administering non conformity with respect to material and work execution.
•
Determining, collecting and analyzing appropriate data to demonstrate the suitability and effectiveness of the quality management system.
•
Coordination with the Owner’s Engineers on all QA/QC matters.
•
Production of concrete and laboratory testing record
QA Manager
Mr. Muhammad Aslam
•
Planning inspection activity and practicing inspection for work.
•
Administering non conformity with respect to material and work execution.
•
Checking inspection results and preparing official reports
•
Review quality of all materials at site and ensure compliance to all project specifications and quality and collaborate with department for all material procurement and maintain quality of materials.
•
Analyze all products and nonconformance processes and evaluate all documents to ensure maintenance of optimal quality
•
Coordination with the Owner’s Engineers on all QA matters.1
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
EHS manager
Rev
Owner’s Engineer 03
: Mr. Tanzeel
•
Avoid all personal injuries during the execution of the Project by targeting to Zero LTI.
•
Ensure that all personnel employed on the Project are competent to carry out their designated tasks safely by supporting continuous HSE training, adequate HSE measures, instruction and supervision.
•
Create positive health, safety and environment attitudes and perceptions at all levels of the Site organization, and to raise health, safety and environmental awareness in general.
•
Implement a training program that supports the achievement of personnel competency in relation to Health, Safety, and the Environment.
•
Carry out all operations related to construction and commissioning with the health and safety of personnel and the impact on the environment as the prime consideration.
•
Complete the site work without incurring any significant property damage to permanent or temporary facilities.
•
Continually monitor and improve HSE performance.
Chief Surveyor
: Fawad Ahmed
•
Create the miniature of the construction plans that would serve as the source of the site plans
•
Keep in touch with the engineering and design personnel’s.
•
The Survey Engineer is considered part of field management and is responsible for various aspects of field engineering and surveying for the project. The Survey Engineer is in responsible/ in charge for all construction layout and survey documentation, and as such (structure alignment, before ,during and after the concrete placement)
•
Works directly with the Field Engineer Manager regarding initial project layout requirements, means and methods of establishing project survey control, and field reporting.
•
Works with Field Engineers in the following tasks: o engage in site layout, construction planning, scheduling, quality control, and job site safety.
•
Provides and maintains horizontal and vertical survey control by use of a level, total station, etc., including organized documentation of survey notes.
•
Assists in the preparation of final records for the project, including as-built.
•
Works with site engineer/foreman to ensure structures are built in conformance with the design alignment and contractual requirements.
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Owner’s Engineer 03
Rev
4. Resources 4.1. Manpower {Table 1 Manpower detail for Horizontal tunnels excavation and support)
Vertical Tunnels S/N
Designation
Day
Night
Horizontal Tunnels Day
Night
1
Shift Engineer
1
1
1
1
2
Surveyor
1
1
1
1
3
Surveyor helper
2
1
2
1
4
Foreman
2
2
1
1
10
10
5
5
05
05
4
4
05
05
4
4
5
5
4
4
12
10
5
5
5
6
7
Steel fixer
Carpenter
Welder
8
Mason
9
Unskilled labor
10
Operators
Total
4
4
2
2
47
44
29
28
Note: Manpower can be changed according to site conditions.
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Rev
Owner’s Engineer 03
4.2. Major Equipment and Tools [Table4: Major equipment for waterway tunnels concrete lining]
S/N
Site
Equipment
Capacity
Work
Excavator (jack hammer)
0.6 CUM
Scaling, trimming
Charging car
2 man basket
Steel plate form
6 M (High)
Rebar fixing
1
Concrete pump
120 m3/hour
Concrete pouring
1
Water pumps
3”
Dewatering, curing
1
Gas cutter
Cutting works
1
Welding machine
Welding works
2
8
vibrators
Concrete pouring
3
9
compressor
750 CFM
Cleaning work
1
10
Generator
500 KW
Power supply
1
Mobile Crane
50 tons
Stationary pump
120 m3/hour
1 2 3
5 6 7
Horizontal tunnels
4
1
3 4 5 6
Vertical tunnels
2
Qty. 1
Cleaning, dismantling, rebar fixing
shifting of steel liner, rebar’s etc.
1
1
Concrete supply
1
Welding machine
Welding works
1
vibrators
Concrete pouring
2
Gas cutter
Steel cutting works
1
chain blocks
shifting of vertical steel
Note: Quantity of above major equipment and tool can be changed due to site conditions
liner
4
Method statement of waterway tunnels concrete lining. Doc. No
DLJV-CONS-MS-WT-02
Owner’s Engineer 03
Rev
5. Flow diagram 5.1 Vertical tunnels lining concrete flow diagram [Figure 2: Sequence of work for waterway vertical shafts excavation & support]
Removal of Existing Temporary facilities
Steel fixing Assembling of liner Erection of steel ribs lining form lifting structure at the top of shaft tunnel
Fixing of Shifting of squeezed liner form at the bottom of vertical shaft
Fixing of steel liner
Pouring of concrete
Survey of alignment and verticality
Survey monitoring
Wait for concrete setting Shifting of liner for next stage
Continuous concrete curing
Method statement of waterway tunnels co...