BLDG2023 Construction Planning 2019 ONM Class Tutorial
Question 1 An overlapping network diagram is given below, activity duration and lead times are given in the diagram. Calculate the project duration and ESDs and EFDs of each activity. (Optional: Floats and LSDs and LFDs of all activities.)
5
4 D
LT = 3
LT = 2 2
0
5
6
A
B
2
6
8
E
G
3
4 C
4
7 F
2
Question 2 An overlapping network diagram is given below, activity duration and lead times are given in the diagram. Calculate the project duration and ESDs and EFDs of each activity. (Optional: Floats and LSDs and LFDs of all activities.)
8 B
6
2
E 2 LT = 1
5
0
11
5
A
C
9 5
3
F
H
2
8 D
5
5 G
11
LT = 3...