TWO CHINA AID BRIDGES PROJECT (TCABP) MANILA, PHILIPPINES

METHOD STATEMENT FOR THE CONSTRUCTION OF TEMPORARY BRIDGE, DRILLING PLATFORM AND BORED PILE For BINONDO-INTRAMUROS (BI) BRIDGE PROJECT

MANILA, PHILIPPINES April, 2019

CRBC/mpa

1|P age

DRILLING PLATFORM FOR BORED PILES

TEMPORARY BRIDGE

RECLAMATION AREA EMBANKMENT

COFFERDAM STEEL SHEET PILES

Revised Plan of North Approach Bridge

2|P age

PART 1: Pier 5, Main Bridge and Pier 6 & Pier PB6, North Bank of Pasig River

PART 2: PIERS 7-9- (Along Estero de Binondo Channel between Muelle dela Industria and Dasmarinas Bridges)

3|P age

PART 3: PIERS B6 TO B13 AND ABUT.B14 (Along Muelle dela Industria Street and Pasig River North Bank Reclamation L=286.45 meters ending at Sta. MK0+565)

PART 4: PIERS 10 TO 22 –(Along Estero de Binondo Channel between Dasmarinas and San Fernando Bridges)

4|P age

Project Update: In coordination with CCCC Highway Consultants Co. Ltd. and the Department of Public Works and Highways (DPWH), they promised to provide the Revised Detailed Engineering Design (DED) of the Binondo-Intramuros (BI) Bridge Project on or before April 20, 2019 and to resume the Works in the project on April 21, 2019. The layout of the equipment/bridge was based on the drawing not officially issued by the Consultant and DPWH for construction. 

PROGRAM OF WORK PART 1: Pier 5, Main Bridge and Pier 6 & Pier PB6, North Bank of Pasig River ITEM

1.0

2.0

3.0 4.0

DESCRIPTION Removal of Power, Communication Lines, Electric Posts, and other Structures

DATE To be completed before April 21, 2019 Construction of Temporary Bridge and April 21- May 31, Platform and Steel Casing at Pier No. 5, Main 2019 Bridge Construction of the 13 Nos. Bored Piles at April 21 – June Pier No. 4, Main Bridge 25, 2019 Construction of the 13 Nos. Bored Piles at June 26 – August Pier No. 5, Main Bridge 31, 2019

REMARKS

PART 2: PIERS 7-9- (Along Estero de Binondo Channel between Muelle dela Industria and Dasmarinas Bridges) ITEM

1.0

2.0

5|P age

DESCRIPTION Removal of Power, Communication Lines, Electric Posts, and other Structures along Estero de Binondo, Binondo, Manila Construction of Temporary Bridge and Platform and Steel Casing at Pier Nos. 7, 8 and 9, along Estero de Binondo between Muelle dela Industria and Dasmarinas Bridges

DATE To be completed before June 26, 2019 June 26 to August 10, 2019

REMARKS

3.0

Construction of the 12 Nos. Bored Piles at Pier Nos. 7, 8 and 9, along Estero de Binondo between Muelle dela Industria and Dasmarinas Bridges

July 26September 25, 2019

PART 3: PIERS B6 TO B13 AND ABUT.B14 (Along Muelle dela Industria Street and Pasig River North Bank Reclamation L=286.45 meters ending at Sta. MK0+565) ITEM

DESCRIPTION

DATE

1.0

Removal of affected Power, Communication Lines, Electric Posts, other Structures and Trees along Muelle dela Industria Street, Binondo, Manila Construction of Cofferdam using Steel Sheet Piles for Embankment at reclamation area along Pasig River North Bank for the construction of Piers PB6-PB13 and AB14 along Muelle dela Industria Street, Binondo, Manila Construction of the 22 Nos. Bored Piles at Piers PB6-PB13 and AB14 along Muelle dela Industria Street, Binondo, Manila

To be completed before April 21, 2019

2.0

3.0

REMARKS

April 21- July 20, 2019

July 21 – October 31, 2019

PART 4: PIERS 10 TO 22 –(Along Estero de Binondo Channel between Dasmarinas and San Fernando Bridges) ITEM

1.0

2.0

3.0

6|P age

DESCRIPTION Removal of Power, Communication Lines, Electric Posts, and other Structures along Estero de Binondo, Binondo, Manila Construction of Temporary Bridge and Platform and Steel Casing at Pier Nos. 10-22, along Estero de Binondo between Dasmarinas and San Fernando Bridges Construction of the 53 Nos. Bored Piles at Pier Nos. 10-22, along Estero de Binondo between Dasmarinas and San Fernando Bridges

DATE To be completed before August 11, 2019 August 11 to November 15, 2019 September 26, 2019- January 25, 2020

REMARKS

Method Statement for the Construction of Temporary Bridge and Drilling Platform

I. Introduction 

Removal of affected MERALCO and TELCO Power and Communication Lines and Trees. Prior to the construction of the Temporary Bridge and Platform for Pier 5, Main Bridge and Piers 6 & B6 at North Bank of Pasig River and North Approach Bridge. Removal, realignment and heightening of Power, Electric and Communication Poles, Lines and Trees will all be cleared by their respective Agencies concerned. These undertakings shall be completed and handover to Contractor by the Department of Public Works and Highways (DPWH) on or before April 20, 2019 and resume Works on April 21, 2019. 1. Stockpile of Materials (800mm.dia. Steel Pipe Piles, 2HM488x300mm, I50bx400mm &I36ax400mm, and 10x300x300mm. Connecting Plates and C25a Channel for Deck Slab of Temporary Bridge is located along Muelle dela Industria Street.

RECLAMATION AREA

Figure 1.0- PIER 5, MAIN BRIDGE, PIER 6 & PIER B6, B7 & B8: Affected MERALCO and TELCO Power and Communication Lines and Trees along Muelle dela Industria Street 7|P age

2. Stockpile of Materials (800mm.dia. Steel Pipe Piles, 2HM488x300mm, I50bx400mm &I36ax400mm, and 10x300x300mm. Connecting Plates and C25a Channel for Deck Slab of Temporary Bridge located along Muelle de Binondo Street.

Figure 2.0- PIER 7: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo & Muelle dela Industria Streets

Figure 3.0- PIERS 8&9: Affected MERALCO and TELCO Power and Communication Lines along Muelle Binondo Street

8|P age

Figure 4.0- PIER 10: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

Figure 5.0- PIER 11: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

9|P age

Figure 6.0- PIER 12: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

Figure 7.0-PIER 13: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street 10 | P a g e

Figure 8.0- PIER 14: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

Figure 9.0- PIERS 15, 16 & 17: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

11 | P a g e

Figure 10.0- PIERS 18, 19 & 20: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

Figure 11.0- PIERS 21&22: Affected MERALCO and TELCO Power and Communication Lines along Muelle de Binondo Street

12 | P a g e

3. Stockpile of Materials (800mm.dia. Steel Pipe Piles, 2HM488x300mm, I50bx400mm &I36ax400mm, and 10x300x300mm, Connecting Plates and C25a Channel for Deck Slab of Temporary Bridge and Steel Sheet Piles for Cofferdam is located along Muelle dela Industria Street.

Figure 12.0- PIERS B9, B10 & B11: Affected MERALCO and TELCO Power and Communication Lines and Trees along Muelle dela Industria Street

Figure 13.0- PIERS B12, B13 & ABUTMENT B14: Affected MERALCO and TELCO Power and Communication Lines and Trees along Muelle dela Industria Street 13 | P a g e

Figure 14.0- RECLAMATION AREA: Affected MERALCO and TELCO Power and Communication Lines and Trees along Muelle dela Industria Street

Figure 15.0-RECLAMATION AREA: Affected MERALCO and TELCO Power and Communication Lines and Trees along Muelle dela Industria Street

14 | P a g e

Figure 16.0-END OF RECLAMATION AREA, STA. MK0+565: Affected MERALCO and TELCO Power and Communication Lines and Trees along Muelle dela Industria Street



Temporary Bridge and Platform Construction The construction of Temporary Bridge and Platform shall commence from the construction and piling of a 3- 800mm.dia. Steel Pipe Piles anchored on the (North Bank) at Muelle de Industria; Stake out Survey shall be undertaken; driving of Steel Pipe Pile for Columns from North Bank Muelle de Industria towards Pier P5 (Temporary Bridge) and continuously done (Drilling Platform) at Pier P5 preparatory for the construction of 13 Nos. Bored Piles and also covered Pier 6 and Pier PB6 of North Bank. The construction shall be done span by span method using Crawler Crane with attached Pile Driving Machine/Vibratory Hammer. After the completion on the Steel Pipe Pile driving, a Connecting Plate will be installed and the installation and assembly of the Cross Beam (2HM488x300) shall be done followed by the installation and assembly for the Longitudinal Beam (I50bx400mm/I36x400mm); Cross and Longitudinal C25ax260mm Channel Deck slab and Guard Rail and Post on both sides of the Temporary Bridge.

15 | P a g e

The Mobile Crane (Telescopic) shall unload the Steel Pipe Piles, “HM” Girders, “I” beams, “C” Channel and the both side Guard Rail and Posts from Trailer Truck with Manpower support and the Crawler Crane lifting and start piling of Steel Pipe Piles and move forward every span of the Temporary Bridge and Drilling Platform. Piling operation shall continue until it completes the works on a given schedule.  Temporary Bridge and Platform Construction Sequence The construction shall commence from a given sequence. 1. Construction 3-800mm.dia. Steel Pipe Piles anchorage at North Bank Muelle de Industria Street, Binondo, Manila; 2. Setting Out Survey of Temporary Bridge and Drilling Platform; 3. Driving and Installation of Steel Pipe Pile Columns (800mm.dia.); 4. Installation of Connecting Plate (10x300x300)mm; 5. Installation and Assembly of Cross Beams (2HM488x300) mm.; 6. Installation and Assembly of Longitudinal Beams (I50b@400)mm & (I26@400)mm.; 7. Installation and Assembly of Cross and Longitudinal C25a@260mm. Deck slab; 8. Installation and Assembly of Guard Rail and Posts

 Construction of Cofferdam and Embankment along Muelle dela Industria Street. Piers B6-B13 through Abutment B14 to Sta. MK0+565. The Reclamation area along Muelle dela Industria Street using Cofferdam and Embankment will be necessary for the construction of the Pasig River Bank in preparation of the construction of Substructure and Superstructure of the North Approach Bridge. The Reclamation area shall be confirmed on final Detailed Engineering Design (DED) to be issued for construction by the Consultant and Department of Public Works and Highways, (DPWH).

16 | P a g e

Equipment and Tools. EQUIPMENT Crawler Type Crane cap. 75 Tons Pile Driving Machine/Vibratory Hammer Mobile Crane Telescopic

NUMBER 2

USE Piling Works

2

Piling Works

1

Backhoe/ Excavator

4

Low- Bed Trailer Wheel Loader

1 4

Boom Truck

1

Dump Truck

10

Lifting/unloading of Steel Pipe Piles and others For Initial Excavation Hauling Loading of materials Hauling of materials Hauling Embankment

Road Roller/Compactor

2

Embankment

Water Truck Submersible Pump

1 3

Embankment For Dewatering

Electric Generator set cap. 50A

3

Speed Boat Acetylene Machine

1 2

Electrical Equipment and Electric motor Navigation Steel Works

Welding Machine

9

Steel Works

Cut-Off Machine

2

Steel Works

Survey Equipment Other Miscellaneous Equipment

17 | P a g e

2 sets Available

Survey Works Support

II.

Temporary Bridge 3-800mm.diameter Steel Pipe Piles Anchorage (North Bank) Method Statement starts the Temporary Bridge anchorage, a 3800mm.dia., Steel Pipe Piles at North Bank; Muelle de Industria described the construction of anchorage towards the construction of Temporary Bridge to the construction of Drilling Platform for Pier 5, Main Bridge including Pier 6 and Pier PB6 at Pasig River North Bank. Prior to the execution of the works, a Work Inspection Request (WIR) shall be submitted for Consultant Engineer’s approval and noted by the DPWH-UPMO Engineer. Once it is approved, piling works shall commence and will be ready for the installation and assembly of beam supports for the first span of the Temporary Bridge.

III.

Construction of Steel Pipe Pile Columns

 Pile Driving Specification Requirements Hereunder are the following:  Pipe Driving is the process of forcing the Steel Pipe Pile into the riverbed ground without excavation.  The Steel Pipe Pile should be driven vertically.  However, a tolerance of eccentricity of 2% of the Steel Pipe Pile length is permissible.  The eccentricity is measured by means of plumb bob.  The equipment required for Steel Pipe Pile driving are as follows: Pile Frame Pile Vibratory Hammer Leads Winch Miscellaneous

18 | P a g e

75 Ton Crawler Crane

Vibratory Hammer Steel Pipe Pile

Deck Platform Main Beam Water

Figure 17.0- Pile Driving  The Method of Piling Works. 1. Delivery of Steel Pipe Piles by Trailer Truck from the Fabrication Plant and lift by a Crane for the commencement of Piling Works. 2. Mobilization of the Crane with Pile Driving Machine /Vibratory Hammer. 3. Lifting the Steel Pipe Pile lower segment by the Crane then mount with the Pile Driving Machine/Vibratory Hammer. 4. Driving the lower segment Steel Pipe Pile. 5. Lifting the Upper segment Steel Pipe Pile and splicing. 6. Driving the upper segment Steel Pipe Pile (Middle Top). 7. Confirm the bearing capacity by evaluating penetration during driving.

IV. Temporary Bridge and Platform Construction InGeneral  Setting out Survey of Temporary Bridge and Platform Prior to the commencement of the survey works, a Work Inspection Request (WIR) shall be submitted to Consultant’s Engineer approval and noted by the DPWH-UPMO Engineer. The location of the Temporary Bridge and Drilling Platform alignment shall be set out and peg by a licensed Surveyor based on approved setting out drawing from Consultant and control points at site. The surveying details of each location to be recorded, incorporating reduced level and coordinates. Each individually 19 | P a g e

surveyed Steel Pipe Pile position shall be protected from disturbance prior to commencement of the Piling works. Two (2) reference points are to be installed for reference checking and monitoring continuously during the execution of the Piling works.  Installation of Steel Pipe Pile Piers-800mm.dia. X 10mm. LAY OUT PLAN OF THE TEMPORARY BRIDGE AND DRILLING PLATFORM AT NORTH BANK AROUND PIER P5

A.

From Muelle de Industria to Pier P5

Figure 18.0- Section and Plan from North Bank to Pier P5

B. Drilling Platform of Pier P5, Main Bridge

Figure 19.0- Plan Pier P5, Main Bridge

20 | P a g e

The specification of Steel Pipe Pile materials is 800mmdia.x 10mm.thk.and length of 32.672meters for one (1) unit Pile as indicated in the drawing or at Top Elevation (+)3.082meters and Bottom Elevation (-) 29.59meters and duly approved by the DPWH and Consultant’s Engineers prior to be allowed for its use. Work Inspection Request (WIR) will be submitted to Consultant’s Engineer approval and noted by the DPWH UPMO Engineer prior to start the construction works. The Piling works of Steel Pipe Pile Columns for the Temporary Bridge and Drilling Platform can be done with Crawler Crane with attached Pile Driving Machine/Vibratory Hammer. Delivery of Steel Pipe Pile Materials is hauled by Trailer Truck from the Fabrication Plant and unloaded by a Mobile Crane for continuous piling operations. The Piling work sequence to adopt could be started from the North Bank at Muelle de Industria towards Pier P5 for the number of spans of the Temporary Bridge consisting of Steel Pipe Pile Columns, Cross and Longitudinal Beams, C25 Channel Deck slab and continuously done at Pier P5 Drilling platform. Following the completed Steel Pipe Pile Columns is the installation and assembly of the 10x300x300mm Connecting Plates; 2-HM488x300mm Cross Beams preparatory for the installation of Longitudinal Beam I 50b @ 400mm (I 36a @ 400mm); C 25a @ 260mm Deck slab; and installation and assembly of Fence (Guardrail and 4.80mm.x150 Posts) both sides. A. At Pier P5- Sections “A-A”; “B-B”; “C-C” and “D-D” 1. Longitudinal Section along “A-A” and “B-B”

21 | P a g e

Figure 20.0- Longitudinal section of the Steel Pipe Pile Column for installation

2. Cross - Section along “C-C” and “D-D”

22 | P a g e

Figure 21.0- Cross-section of the Steel Pipe Pile Columns for installation

23 | P a g e

Figure 22.0- PIERS 7, 8 & 9: Plan and Section of Temporary Bridge and Drilling Platform along Estero de Binondo

Plan 24 | P a g e

Section Figure 23.0- PIERS 10 TO 22: Plan and Section of Temporary Bridge and Drilling Platform along Estero de Binondo

ILLUSTRATION # 1:

Figure 24.0- Piling Operation of the Steel Pipe Pile Columns (800mmdia.)

25 | P a g e

ILLUSTRATION#2

Figure 25.0- Installation and Assembly of Cross Beams (2HM488x300)

ILLUSTRATION#3

Figure 26.0- Installation and Assembly of Longitudinal Beam (I50bx400) & I36x400)mm.

26 | P a g e

ILLUSTRATION#4

Figure 27.0- Installation and Assembly of Cross C25a Channel Deck slab

ILLUSTRATION#5

Figure 28.0- Installation and Assembly of Guardrails (Post and Railing)

27 | P a g e

Furthermore, the Crawler Crane shall continuously doing the piling of the Steel Pipe Pile Column for Temporary Bridge and Platform at Pier P5 and systematically Span by Span for the installation and Assembly of the 10x300x300mm Connecting Plates; 2-HM488x300mm Cross Beam preparatory for the installation and Assembly of Longitudinal Beam I 50b @ 400mm (I 36a @400mm); C 25a @ 260mm Cross Deck slab and Installation of Fence (4.80mm.dia. Fence and 4.80mm dia.x150 Posts) both sides.

A joint inspection and acceptance of the completed Works shall be dealt with Consultant, DPWH-UPMO and Contractor’s representatives prior to the commencement of Main Bridge Substructure Works operation.

 Installation of 10x300x300mm Connecting Plate.

Connecting Plate with the Cross Beam Beam 2-HM488x300

Connecting Plate 10x300x300mm 10mm 10mm

Shear Brace HM488x300 mm 800mm.dia. x10mm Steel Pipe

Figure 29.0- Connecting Plate on Steel Pipe Pile  Installation of the 10x300x300mm. Connecting Plate welded on the Steel Pipe Pile 800mm.dia.10mm thick with support Manpower.

28 | P a g e

 Installation of a 2-HM488x300mm. Cross Beam Cross Beam 2-HM488x300mm.

800mm.dia. x10mm Steel Pipe

Figure 30.0- Cross Beam installed on Connecting Plate  Installation of a HM488x300mm Shear Brace cross bolted below a 2HM488x300mm Cross Beam with 800mm.dia. x 10mm Steel Pipe Pile using Manpower support.  Installation and Assembly of a 2HM488x300mm Cross Beam lifted with the use of a Crawler Crane and Manpower support.  Installation of I50b @ 400mm. Longitudinal Beam Longitudin...