ASSIGNMENT 2 FRONT SHEETQualification BTEC Level 5 HND Diploma in BusinessUnit number and title Unit 16: Operations and Project Management (528)Submission date October 18th, 2020 Date received (1st submission) October 18th, 2020Re-submission date Date received (2nd submission)Group number:Student na...
ASSIGNMENT 2 FRONT SHEET Qualification
BTEC Level 5 HND Diploma in Business
Unit number and title
Unit 16: Operations and Project Management (528)
Submission date
October 18th, 2020
Date received (1st submission)
October 18th, 2020
Date received (2nd submission)
Re-submission date Student names & codes
Final scores
Signatures
1. Nguyen Cong Dung – GBH190280
CDung
2. Le Minh Nghia – GCH16061
MNghia
3. Le Viet Long – GBH18685
VLong
4. Pham Thanh Long – GBH18747
TLong
5. Vu Tien Duc – GBH18252
TDuc
Group number:
Class
GBH0803
Assessor name
Pham Thi Hoang Yen
Student declaration I certify that the assignment submission is entirely my own work and I fully understand the consequences of plagiarism. I understand that making a false declaration is a form of malpractice. P3
P4
M3
M4
D2
OBSERVATION RECORD Student 1
Nguyen Cong Dung – GBH190280
Description of activity undertaken
Assessment & grading criteria
How the activity meets the requirements of the criteria
Student signature:
Date:
Assessor signature:
Date:
Assessor name:
Student 2
Le Minh Nghia – GCH16061
Description of activity undertaken
Assessment & grading criteria
How the activity meets the requirements of the criteria
Student signature:
Date:
Assessor signature:
Date:
Assessor name:
Student 3
Le Viet Long – GBH18685
Description of activity undertaken
Assessment & grading criteria
How the activity meets the requirements of the criteria
Student signature:
Date:
Assessor signature:
Date:
Assessor name:
Student 4
Pham Thanh Long – GBH18747
Description of activity undertaken
Assessment & grading criteria
How the activity meets the requirements of the criteria
Student signature:
Date:
Assessor signature:
Date:
Assessor name:
Student 5
Vu Tien Duc – GBH18252
Description of activity undertaken
Assessment & grading criteria
How the activity meets the requirements of the criteria
Student signature:
Date:
Assessor signature:
Date:
Assessor name:
Summative Feedbacks: Resubmission Feedbacks:
Grade:
Assessor Signature:
Internal Verifier’s Comments:
Signature & Date:
Date:
Table of Contents I.
Introduction ................................................................................................................................................ 9
II.
Main content of the report ......................................................................................................................... 9 1.
Business Case: Lean production improvement in Traphaco .................................................................... 9
2.
Four keys stage of PLC ........................................................................................................................... 11
3.
2.1
Initiating ......................................................................................................................................... 11
2.2
Planning.......................................................................................................................................... 11
2.3
Executing ........................................................................................................................................ 16
2.4
Project Closure................................................................................................................................ 17
Evaluation of theory applications into the project ............................................................................... 19 3.1
Project Lifecycle .............................................................................................................................. 19
3.2
Project Management ..................................................................................................................... 20
3.3
Leadership ...................................................................................................................................... 21
3.4
Agile and Traditional Method ........................................................................................................ 21
4.
Evaluation application of tools .............................................................................................................. 21
5.
Expand the project ................................................................................................................................ 22
III.
Conclusion ............................................................................................................................................. 23
IV.
References ............................................................................................................................................. 24
V.
Appendix ................................................................................................................................................... 24
I.
Introduction
In this mission, we will take responsibility for strategic consulting of E&Y company and our client is Traphco company. Our team of 5 people will research and improve operating procedures for Traphaco. We will research on the lean method and advise Traphaco to be able to understand and apply replacement on the transmission line. Below will apply the PLC to the project, including 4 phases of initiation, planning, execution and closure. Including important documents such as WBS, Task allocation, Gantt chart ... Then will evaluate and comment on the effectiveness of PLC in this project. Below are detailed assessments that cover the strengths and weaknesses of applying a PLC. II.
Main content of the report
1. Business Case: Lean production improvement in Traphaco Background: Continuing our foundation from the gaps we learned in Traphaco's operations, as a consultant working for Ernst & Young, we were assigned to join a group of 5 in the 10-day project assisting Traphaco in improving its operational apparatus. Specifically, our team is expected to give opinions, prepare a plan for further research, discuss with representatives of the company ... to collect and analyze data, see consider theoretical or implemented solutions. Traphaco Pharmaceutical and Medical Equipment Joint Stock Company officially started operating in the form of a joint stock company with 45% state capital. At the same time, maintain the Traphaco brand as the most famous brand in the Vietnamese pharmaceutical industry with the best product quality and service quality (vnr500, 2019). At Traphaco, the company applies a comprehensive Total Quality Management (TQM) policy to increase its competitive edge in the healthcare sector (Minh, 2014). However, in order to develop stronger in the operation management, we - under the consulting firm of E&Y, will analyze and propose other methods of application for Traphaco. Scope: Performing in 10 days to apply Lean production to reduce labor cost and increases stability for product quality of Traphaco Human resources: •
Nguyen Cong Dung - Team leader is responsible for urge and assign work to the members and synthesize all the documents that the members have been preparing. Schedule meetings and ensure the highest quality of meetings.
•
Le Minh Nghia - The managing is in charge of monitoring the members so that documents are submitted on time. In addition, the deputy team is also responsible for motivating and balancing for everyone.
•
Le Viet Long - Secretary has the experience to take notes and synthesize the contents of the meeting and write reports as well as remind the members to complete the tasks on time.
•
Pham Thanh Long - team member is responsible for writing marketing content to attract customers so that they understand the purpose of the project
•
Vu Tien Duc - Sponsor is responsible for covering 50% of the costs of meetings and collecting data (if any) in addition to also holding diplomatic functions to negotiate and transmit information to clients.
Project Time: From 3rd October 2020 to 13th Otober 2020 Key objective: -
Traphaco: helps Traphaco better understand the limitations and benefits of applying lean product in businesses
-
Help Traphaco apply effective Lean Production to improve operations within the company
Key Stakeholders: - Customers: Traphaco - The application of Lean production to the production process will directly affect the company's output in terms of quality, followed by the company's revenue. - Top management: E&Y - The success or failure of the project will also affect E&Y, especially in terms of the prestige and trust of customers in them. - Team members: After the project is completed and recognizing the effectiveness that the project can do for customers - Traphaco, team members will receive a salary increase, increasing their reputation for E&Y, Traphaco and customer future goods. Risks and Solution -
Customers may not see the feasibility of the project
Provide specific evidence from the collected data to make the project more feasible or give the customer direct data about the project's report, thereby helping the customer to better visualize the project. project quality. -
Team members can sometimes have conflicts that affect the quality of the project
Sometimes the group has certain conflicts, Mr. Nghia is always the person who promotes and makes the group more united to avoid affecting the project. For example, every time the project is dead. Minh Nghia always making fun for everyone increases team spirit, thereby positively influencing members to complete the project on time, making the project quality better. -
Group members sometimes have their own affairs and are not present at the meeting
Other members record and transmit information to the absent member that day 2. Four keys stage of PLC 2.1 Initiating First, when we started to want to do the project, we started to choose members to perform this task and the 5 people we have include: Nguyen Cong Dung, Le Minh Nghia, Vu Tien Duc, Pham Thanh Long and Le Viet Long. Next, we started to learn about the project we chose, from there, we calculated the scope, cost and risk, the project started on 3 October and ended on 13 months. 10. We elect Nguyen Cong Dung as Leader, Le Minh Nghia as Management, Vu Tien Duc as the sponsor, Le Viet Long takes over the transcription of their meetings and Pham Thanh Long will be the person who communicates. customer. Although each person plays a role for the project, sometimes people still help each other, thereby giving everyone a spirit of solidarity mixed with self-awareness with their tasks. From the above, we are confident that on this project we will be successful with the team's idea. 2.2 Planning Work Breakdown Structure
Task Allocation Activities
In Charged
Outcome
Project Discussion
All Member
Unify
Timescales
project
allocate
task
idea, 3rd October 2020 – steps, 5th October 2020
assign each member’s duties, Determine work methods,
Background,
Scope, Resource, Time, Key
objective,
key
stakeholder and risks Preparation
for
the All Member
process
Contact Sponsor, Work 5th October 2020 Schedule,
Budget
Balance Implementation
of All Member
report templates
Find
out
about
Presentation
to 7th October 2020
customers
the Viet Long
Currently, Traphaco only 10th October 2020
current
status
Traphaco
of
applies
Lean
Lean
to
the
teardrop production line
Production Find information about Minh Nghia
Only, Traphaco is at the 10th October 2020
Lean
forefront
Production
of
in
the
domestic pharmaceutical
application of lean in the
companies
pharmaceutical industry, while other companies are one of the few that have not applied lean yet.
Learn
about
Lean Cong Dung
Production
of
foreign 10th October 2020
Mostly pharmaceutical
international
companies use Lean in
pharmaceutical
production lines and can
companies
be mentioned Johnson & Johnson – the largest pharmaceutical company in the world.
Comparison Production
of
Lean Thanh Long
between
domestic
The reality of lean in 11th October 2020 Vietnam is still very poor
and
compared
to
the
international
international one
The risk that Traphaco Tien Duc
Currently,
faces if applying Lean
machines to use lean is
Production
still
relatively
importing 11th October 2020
difficult
because the economy and technology are not high. Risk Management
All Member
Foreseeing the risks that 11th October 2020 the team will encounter
while
completing,
thereby giving solutions to the whole group Cost Management
All Member
Manage the expenses 10th October 2020 necessary to complete the project
Organize
member’s All Member
Manage members' work 12th October 2020 by checklist
meeting The report is completed
All Member
10th October 2020
Presented to customers
All Member
13th October 2020
Gantt Chart
(Templates, 2020)
Budget Date
Description of work
Cost per person
3/10
Set up teamwork
250.000VND
6/10
Discuss/ summary information
130.000VND
7/10
Meeting for doing WBS/ Gant chart
250.000VND
10/10
Evidence, thesis / meeting customers
280.000VND
13/10
Final report
120.000VND
Total
1.030.000VND
2.3 Executing All preparations are going as planned in the project. When group discussion takes place by group members. Sometimes there was some internal problem with the wrong original plan, we misunderstood this project report it caused us to slow the project down from the schedule shown in the WBS, Gant chart. Moreover, the timing manage of our team is not good so in planning phase we can't keep track the schedule. The normal working process of the group encountered disagreement in the process of working together, resulting in financial difficulties as well as working together in a group with many elderly people working so. The group solved these problems by planning ahead and choosing the group's free time to work so that all 5 people can help and support each other's interactions to understand each other's thinking to speed up work in the project. In the group issue, we look for relevant documents such as Traphaco's annual reports, in addition to other primary data that we collect to help the team understand better and on time be selected so it is quick and easy. Most of the information that the group has found has met the necessary criteria because the group has understood the nature of the project and is going as expected, before that, in the early days of the project, the group misunderstood the project, causing the conflict extremely stressful and anxious. Nguyen Cong Dung - Team leader is responsible for urging and assigning tasks to members, at the same time synthesizing all prepared member profiles, scheduling the meeting and ensuring the highest quality of the meeting. Le Minh Nghia - Head of department in charge of monitoring the members who submit dossiers on time. In addition, the vice-captain is also responsible for creating motivation and balance for everyone. Le Viet Long - Experienced Secretary takes notes, synthesizes meeting contents and writes
report as well as reminds members to complete tasks on time. Pham Thanh Long - team member is responsible for writing marketing content to attract customers so that they understand the purpose of the project. Vu Tien Duc - Sponsor is responsible for supporting 50% of meeting costs and collecting data (if any). We exchange information primarily through Messenger and Discord. But I find Messenger really ineffective because it distracts people while working, people will be distracted when someone else's message arrives. So through Discord, we exchange information directly and can see the faces of our team members so we can convey more accurate information. The leadership style that the group applies is the democratic style, in particular Cong Dung will be the leader. He always asks for opinions and collects feedback from team members before making a final decision. As a result, team members feel more respected and motivated to work, which in turn promotes higher employee engagement and work satisfaction. 2.4 Project Closure Project evaluation: According to the objectives of the project, based on contributions and systematic review to determine the effectiveness, the level of success and the impacts that can affect the set objectives, in addition to synthesizing from the members of the team, besides the elements assessed by the project KPI such as Cost, Quality, Time, our project has basically been completed and succeed. Thereby we have been given a recommendation to deliver to customers. Team evaluation: In general, the team members completed their assigned tasks although at first the group management was not good, everyone worked well together for common purposes so the project looked joint completed. Team members are also respectful of each other's opinions throughout the working process, sometimes there are conflicts, but only small issues, do not affect too much on the project. All team members are highly disciplined, with a common goal of completing the project. In addition, the personalities of the group members match well despite the difference ...