Cloud Migration Executive Brief August 2019
Current Operations All APIs are currently hosted on a local server. The server, while still functional, is ending its technological end of life. No additional upgrades can be accommodated. Projections of increased customer base reveal the need for future expansion of hardware and computing capabilities. Server administration team of the IT department is comprised of
2
Future Operations All APIs are currently hosted in reserved Public Cloud Cloud Service Provider (CSP) guarantees SLAs for availability. (Monitoring/Availability risk transferred to CSP) Virtual compute environment affords the opportunity to scale as demand requires. (No hardware upgrade purchase) Personnel reduction of 60% possible with 36 months.
3
Cost Area (Current)
Cost Analysis
Function
Cost
Data Center
Labor/Salary
$280,000
Data Center
Hardware
$6,000/yr
Data Center
Electric/HVAC
$48,000/yr
Support Staff
Labor/Salary
$406,250/yr
Total
Remarks 8 Personnel
10 Personnel
$740,250/yr
Cost Area (New)
Function
Cost
Remarks
Virtual Data Center
Initial Invest
$202,000
One-time setup
Annual
$101,000/yr
Exceeds current HW specs
Data Center
Labor/Salary
$174,999/yr
3 Personnel
Support Staff
Labor/Salary
$81,250/yr
2 Personnel
Virtual Data Center
Total Savings
$559,047/yr $181,203/yr
Not incl. Setup Cost 4
COMPARISON
Advantage
Disadvantage
Relief from expensive hardware upgrades and continued electrical, HVAC expenses
Internet connection required for administration
Reduction of personnel expenses by over 60%
Public cloud introduces new vulnerabilities
Transfer of availability risk to CSP
• •
Risk can be mitigated Reliance on CSP to secure
Enhanced COOP/Disaster Recovery capabilities Reduce carbon footprint •
Environmental impact
5
• Present to shareholders/stakeholders by Q3, 2019
Timeline
• Personnel Training completed by Q3, 2019 • Acquisition of services to be completed by Q4, 2019 (ROI by Q4, 2019)
• Migration of data completed by Q4, 2019
• Staff reductions completed by Q4, 2021
6
Questions
7...