10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

Quiz for Simulaon Game Due No due date

Points 50

Questions 22

Available Oct 2 at 2pm - Oct 5 at 11pm 3 days

Time Limit 60 Minutes

Instrucons This is an individual quiz. Discussions about this quiz with any other students in the class are prohibited during the quiz time. You have 60 minutes to complete the quiz once you start it. You can do it during any 60 minute period between Friday (Oct 2) evening 7:00pm and Monday (Oct 5) evening 11:00pm. You can access the game site at the following URL (will need your team name and password): For Baltimore Section: http://op.responsive.net/lt/busi634ba/entry.html (http://op.responsive.net/lt/busi634ba/entry.html)

For Shady Grove Section: http://op.responsive.net/lt/busi634sg/entry.html (http://op.responsive.net/lt/busi634ba/entry.html)

Aempt History LATEST

Attempt

Time

Score

Attempt 1

35 minutes

32 out of 50

Score for this quiz: 32 out of 50 Submitted Oct 4 at 7:39pm This attempt took 35 minutes.

Question 1

2 / 2 pts

The Littlefield simulation game has a timeframe. We will play the game in the following time frame.

https://umd.instructure.com/courses/1286017/quizzes/1369444

1/13

10/4/2020

Correct!

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

From Day 51 through Day 218

Question 2

2 / 2 pts

True or False: The demand distribution in the future will be similar to that in the first 50 days.

Correct!

True

Question 3

2 / 2 pts

Once the game starts, how many simulation days will pass per real minute?

Correct!

1.6 days

https://umd.instructure.com/courses/1286017/quizzes/1369444

2/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

Question 4

2 / 2 pts

Ture or False: The incoming demand a team will see will be influenced by how the team plays the game.

Correct!

False

Question 5

2 / 2 pts

The process of the factory consists of how many steps? Write an integer number: ____ steps.

Correct!

orrect Answers

4

4 steps 4 Four Four steps

Question 6

https://umd.instructure.com/courses/1286017/quizzes/1369444

2 / 2 pts

3/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

The factory consists of how many stations? Write an integer number: ___ stations.

Correct!

orrect Answers

3

Three 3 Three stations 3 stations

Question 7

2 / 2 pts

What is the fixed ordering cost the factory has to pay every time an order of raw kits is placed?

Correct!

$1000

Question 8

0 / 2 pts

True or False: Every step of the process has a nonzero setup time. https://umd.instructure.com/courses/1286017/quizzes/1369444

4/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

ou Answered

True

orrect Answer

False

Question 9

0 / 2 pts

The cash on hand earns some interest if it is not used to buy machines or raw kits. The compound interest rate is:

orrect Answer

10% per year

ou Answered

20% per year

Question 10

2 / 2 pts

You are allowed to use any of the following batch sizes except:

Correct!

10 kits per lot

https://umd.instructure.com/courses/1286017/quizzes/1369444

5/13

10/4/2020

Unanswered

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

Question 11

0 / 4 pts

Suppose the second pricing contract (i.e., the contract with quoted lead time 1 day) is used. If an order is completed with a lead time of 0.5 days, how much can this order earn? $ If an order is completed with a lead time of 2 days, how much can this order earn? $

Answer 1: ou Answered

(You left this blank)

orrect Answer

1000

orrect Answer

$1000

orrect Answer

1000.0

orrect Answer

1000.00

orrect Answer

$1000.0

orrect Answer

$1000.00

orrect Answer

1,000

orrect Answer

$1,000

Answer 2: ou Answered

(You left this blank)

https://umd.instructure.com/courses/1286017/quizzes/1369444

6/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

orrect Answer

$750

orrect Answer

750

orrect Answer

$750.0

orrect Answer

750.0

orrect Answer

$750.00

orrect Answer

750.00

Question 12

0 / 4 pts

Suppose the third pricing contract (i.e., the contract with quoted lead time 0.5 day) is used. If an order is completed with a lead time of 0.75 days, how much can this order earn? $ 1250 If an order is completed with a lead time of 2 days, how much can this order earn? $ 1000

Answer 1: ou Answered

1250

orrect Answer

625

orrect Answer

$625

orrect Answer

625.0

orrect Answer

625.00

orrect Answer

$625.0

https://umd.instructure.com/courses/1286017/quizzes/1369444

7/13

10/4/2020

orrect Answer

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

$625.00

Answer 2: ou Answered

1000

orrect Answer

0

orrect Answer

$0

orrect Answer

0.0

orrect Answer

$0.0

Question 13

0 / 2 pts

What is the total cost of raw kits in an order? Write an integer number: $___

ou Answered

orrect Answers

10

$600 600.00 600 $600.0 600.0 $600.00

Question 14

https://umd.instructure.com/courses/1286017/quizzes/1369444

2 / 2 pts

8/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

What is the lead time (in days) to receive an order of raw kits after the order is placed? Write an integer number.

Correct!

orrect Answers

4

4.0 4.00 Four days 4 days Four 4

Question 15

2 / 2 pts

What is the initial number of machines at Station 2? Write an integer number: ___ machine(s).

Correct!

orrect Answers

1

1.0 machine One machine 1 machine 1.0 1 1.00 One

Question 16 https://umd.instructure.com/courses/1286017/quizzes/1369444

0 / 4 pts 9/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

In the inventory policy for ordering raw kits used, what is the order quantity Q currently used in the game? 60

raw kits

What is the reorder point R currently used in the game? 100

raw kits

Answer 1: ou Answered

60

orrect Answer

7200

orrect Answer

7,200

orrect Answer

7200.0

orrect Answer

7,200.0

orrect Answer

7,200.00

orrect Answer

7200.00

Answer 2: ou Answered

100

orrect Answer

1200

orrect Answer

1,200

orrect Answer

1200.0

orrect Answer

1200.00

orrect Answer

1,200.0

orrect Answer

1,200.00

https://umd.instructure.com/courses/1286017/quizzes/1369444

10/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

Question 17

2 / 2 pts

What is the purchasing price of a board stuffing machine? It is $____

Correct!

orrect Answers

90,000

$90,000 $90,000.0 90000 $90000.0 90000.0 90,000.0 $90000 90,000

Question 18

2 / 2 pts

What is the average number of orders coming in over the first 50 days?

Correct!

Between 7 and 8

https://umd.instructure.com/courses/1286017/quizzes/1369444

11/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

Question 19

2 / 2 pts

What is the average number of orders completed over the first 50 days?

Correct!

Between 7 and 8

Question 20

2 / 2 pts

What is the average lead time of the orders completed in the first 50 days?

Correct!

Between 1 and 1.5 days

Question 21

https://umd.instructure.com/courses/1286017/quizzes/1369444

2 / 2 pts

12/13

10/4/2020

Quiz for Simulation Game: BUSI634-BA01,GS01: Operations Management-Fall 2020 zlchen

What is the average utilization of Station 1 in the first 50 days?

Correct!

Between 80% and 90%

2 / 2 pts

Question 22

What is the average utilization of Station 2 in the first 50 days?

Correct!

Between 80% and 90%

Quiz Score: 32 out of 50