Midterm exam for L1-L6 with answers...
Multiple Choice Questions:
Q1. Which of the following is not part of the triple constraint of project management? (1 Mark)
● ● ● ●
Meeting scope goals Meeting time goals Meeting communications goals Meeting cost goals
Q2. A ________ is a group of related projects managedinacoordinated way to obtain benefits and control that are not available from managing them individually. (1 Mark)
● ● ● ●
Project Program Portfolio Plan
Q3. Even though a company might work on similar projects over and over again, such as building houses, providing training courses, or developing specific types of products, there are unique challenges because all projects involve ____________. (1 Mark)
● ● ● ●
People Competition Progressive elaboration Uncertainty
Q4. A _____________ provides leadership and direction for project managers working on related projects. (1 Mark)
● ● ● ●
Senior manager Senior project manager Team leader Program manager
Q5. The main purpose of a stakeholder management strategy is to _________________. (1 Mark)
● ● ● ●
Increase the support of stakeholder throughout the project Identify key stakeholders on a project Get senior management support for a project Get key resources needed for a project
Q6. A RACI chart is a type of _______________. (1 Mark)
● ● ● ●
Project organizational chart Resource histogram Responsibility assignment matrix Project dashboard
Q7. On a RACI chart, which letter can only appear once for a task? (1 Mark)
● ● ● ●
R A C I
Q8. Topics such as who will receive project informationandwhowillproduce it, suggested methods or guidelines for conveying the information, frequency of communication, and escalation procedures for resolving issues should be described in a _______________. (1 Mark)
● ● ● ●
Communications management plan Staffing management plan Team contract Scope statement
Q9. A __________________ is a condition or capability that must be met or possessed by a system, product, service, result, or component to satisfy a contract, standard, specification, or other formal document. (1 Mark)
● ● ● ●
Requirement Scope Quality WBS
Q10. What is the first step in planning a project schedule? (1 Mark)
● ● ● ●
Developing a budget Developing an activity list Assigning resources to the project Determining activity sequencing
Q11. What is the most common type of dependency between activities? (1 Mark)
● ● ● ●
Finish-to-start Start-to-finish Start-to-start Finish-to-finish
Q12. The ____________ method is a network diagramming technique used to predict total project duration. (1 Mark)
● ● ● ●
PERT Gantt chart Critical path Crashing
Q13. Requirements documents and a WBS are planning outputs for the project ____________ management knowledge area. (1 Mark)
● ● ● ●
Integration Scope Quality Time
Q14. Activitylists,activity attributes,andmilestoneslists areplanningoutputs for the project ____________ management knowledge area. (1 Mark)
● ● ● ●
Integration Scope Quality Time
Q15. Who determines what quality level is acceptable on a project? (1 Mark)
● ● ● ●
The sponsor The customer The project manager The project team
Q16. Quality _________ includes identifying which quality standards are relevant to the project and how best to satisfy those standards. (1 Mark)
● ● ● ●
Planning Assurance Control Management
Q17. What two dimensions should you use when evaluating project risks? (1 Mark)
● ● ● ●
Probability and impact Cost and schedule Negative and positive Source and responsibility
Q18. What does the S stand for in a SWOT analysis? (1 Mark)
● Strategy
● Systems ● Solutions ● Strengths
Q19. A project ________ is an uncertainty that can have a negative or positive effect on meeting project objectives. (1 Mark)
● Risk ● Opportunity ● Contingency plan
Q20. In risk management, it is important to find the _______ or underlying reason a problem occurs. (1 Mark)
● ● ● ●
Political Cultural Root cause Statistical...