Title | Lecture 6 - Certificates, payment and retention |
---|---|
Author | Jonathan Guy |
Course | Construction Contracts |
Institution | Loughborough University |
Pages | 7 |
File Size | 281.6 KB |
File Type | |
Total Downloads | 41 |
Total Views | 148 |
Construction Contracts. Lecture 6 - Certificates, payment and retention. Achieved a 1st in this module. Lecturer Prof Wayne Lord....
Certificates, payment and retention Payments
Time cost quality and risk – commercial decisions are all about money Interim payment vital to the economics of the construction industry Without interim payments and you would get the money in one go o Cash flow issues o Contractor funding the project themselves o Clients shouldn’t get the supply chain to fund the project themselves o Contractors often have trade credit to fund their own works, then recycle the money they receive on the open market to make more. Keep hold of money, delay payment as long as possible o Pay when paid clauses are illegal o Pay when certified and pay what certified clauses are illegal Can put them in, but they are unenforceable o Housing grants construction and regeneration act 1996 (Construction act) Payment provisions governed by this
Payments – Latham’s recommendation for a modern contract
Provision for assessing interim payments by method other than monthly valuation i.e. milestones activity schedules or payment schedules. Aim to phase out the traditional system of monthly measurement but meanwhile provision should still be made for it. o Clients prefer fixed fees, they don’t like calculated amounts
Payments – Lathams recommendation for a modern contract
Clearly set out period for interim payments Otherwise an automatic right to compensation, involving payment of interest to deter slow payment. o Statutory rate of interest 8% above base – if contract does not make provision o Additional fixed sum can be recovered for non-payment depending debt value o Can recover, compensation for the time/ legal fees/ debt collectors.
NEC4 Payment provisions
Contractor submits application for payment Project manager assess amount due o If contractor does not submit an application for payment - project manager still has to value works o Incentive for the contractor to submit the valuation Assessment interval (Usually one month)
Value of work done to date Other amounts to be paid to the contractor Loss + Expense, Compensation events o Less amounts to be paid by or retained from contractor Retention, MCD, Defective works Price for work done to date under the various options o A – Based on activity schedules – Less descriptive Contractor gets paid for completed activities Activity – is a section of work (fitting out a room, if the projector was not in, the contractor would not get paid anything even though they have done the rest of the works) o B – Bill of quantities – More descriptive Contractor gets paid whatever he puts in based on the BOQ BOQ – The contractor would be paid everything in the room minus the cost of the projector o C to F – Defined costs forecast plus Fee Cost reimbursement contracts. Contractor gets paid the costs plus overheads and profit Other points o Retention percentage By default NEC does not have retention (Optional clause) Rights to suspend o If client has not paid by the final date for payment o Contractor entitled to EOT and costs in maintaining site security and re-mobilisation Costs are added to the contract sum o Walk off site and it is a repudiatory breach which means the other party can kick you off site o If the employer fails to pay, statutory right to suspend performance upon 7 days notices – construction act o o
NEC Payment timescale
The project manager to issue notice on time - cannot just issue a pay less notice instead o Misconception in the industry The project managers certificate is the notice of payment
If employer wants to pay less than the notified sum - issue a pay less notice Final date for payment 14 days from certificate
JCT Payment Provisions
Contractor submits application for interim payment o Alternative A - stage or Fixed sum o Alternative B – Gross valuation) Due date is o 7 days after the interim valuation date or o 7 days after date of receipt by employer of application Employer payment notice within 5 days of due date Final date for payment 14 days from due date Retention deducted o Held by employer Held on behalf the contractor – The contractors money Held in separate bank account (If contractor requests) Money protected in case of insolvency o Retention held – To encourage the contractor to complete the works and/ or to rectify defects o Retention JCT – no obligation to invest retention. Holding it as a trustee. o Retention percentage - 3% standard o ½ released after practical completion Alternative is a retention bond No payment by employer o Contract entitled to simple interest Can suspend – 7 Days statute o NEC based on statue, JCT is a contractual right to suspend
JCT payment cycle:
Construction Act
If the contract is defective these take precedence as a matter of law and cannot be changed Amount due as calculated as
A equal to the value of any work performed during the relevant period B an amount equal to the value of any materials manufactured on site or brought onto site for the purposes of the works o C any other amount or sum which the contract specifies shall be payable during the relevant period Adequate mechanism - For interim or stages payment Payment notices o Payee notices in default o Have to issue payment notices o o
Construction Act Notices
Payment notice (Sum considered to be due at the payment due date and the basis of the calculation) o Payer to payee – Normal o Payee to payer - Not normal but there can be provisions in the contract. Similar to invoice Payee may give notice any time after payer notice should have been given IF sum payee considers will be due at the payment due date and the basis of the calculation o Payee application
Construction Act - Notified sum
Notified sum to be paid on or before the final date for payment Notice of intention to pay less than the notified sum – Pay less notice Clients try to extend the period for final date for payment
Construction Act
Payment cycle o Payment due 7 days following the relevant period or when a claim is made by the payee o Payment notice within 5 days o Pay-less notice not later than 7 days before the final date for payment o Final date for payment, 17 days after due date – for interim payment o For final payment it is 30 days – why?
Statutory payment provisions – 1 – Normal
Statutory payment provisions – 2 – No notice
If no notice is issued, this extends the final date for payment – Someone has to issue the notice Then there will be no final date for payment
Statutory payment provisions 3 – Payee notice
Application for payment may become the notice, if there is no payer notice. This is if no notice has been issued but an application has been. If project manager, then issues payment notice late and halves the valuation – you would be entitled to the full application amount.
Remedies for non-payment
Right to suspend works – if not paid in full o Even if the clause is deleted out the contract the statute law applies o 7 days notice required o Automatic EOT for suspension o Plus reasonable costs
Other
Payment schedule Don’t miss the payment run – happens with larger clients Look at contractors payment cycle and subcontractors payment cycle to ensure cash flow works Cost benefit analysis of retention and retention bond Contractor cannot interfere/ influence the issue of the certificate, has to be independent Bonds
Wates Construction V Frantom – Retention in separate account
Construct a hotel Contractor requested that retention be placed into a separate bank account Employer refused Employer should be a trustee not a beneficiary of the fund Had a duty to safeguard the fund for beneficiaries
Sutcliffe V Tackrah – Certifying Uncompleted works
Employed architects who issued interim certificates Contractor was kicked off site for poor works and went into liquidation Employer sued architects for certifying work not completed Even though the certificate was in error, client is bound to pay the contractor based on the architects certificate...