Quiz week 11: INFOSYS 220: Business Systems Analysis

Quiz week 11 Due May 30 at 22:00

Points 1

Questions 10

Available Mar 8 at 0:00 - May 30 at 22:59 3 months Allowed Attempts 3

Time Limit 20 Minutes

Instructions 3 randomly selected questions on Testing, validation and pre-implementation. 3 randomly selected questions on System conversion strategy. 1 randomly selected questions on System operations and maintenance. 1 randomly selected question on Security. 2 randomly selected questions on Agile. Your highest mark across all attempts will be your final mark.

Take the Quiz Again

Attempt History Attempt

Time

Score

KEPT

Attempt 2

5 minutes

0.9 out of 1

LATEST

Attempt 2

5 minutes

0.9 out of 1

Attempt 1

5 minutes

0.75 out of 1

 Correct answers are hidden. Score for this attempt: 0.9 out of 1 Submitted May 29 at 21:29 This attempt took 5 minutes.

Question 1

0.1 / 0.1 pts

In 1996, Hershey’s set out to upgrade its patchwork of legacy IT systems into an integrated ERP environment. The project consulting team suggested various testing phases to mitigate potential issues. https://canvas.auckland.ac.nz/courses/62082/quizzes/65904

1/7

5/29/2021

Quiz week 11: INFOSYS 220: Business Systems Analysis

In the first testing phase, the key users test the frequently used business scenarios, one department at a time. What type of testing is this?

Acceptance testing

Question 2

0.1 / 0.1 pts

Which of the following support, demonstrate, or, are examples of traceability: [select all appropriate options]

The requirements/traceability pyramid.

The double v-model.

The requirement to get your Group Assignment Proposal approved before you can progress with your final deliverable.

https://canvas.auckland.ac.nz/courses/62082/quizzes/65904

2/7

5/29/2021

Quiz week 11: INFOSYS 220: Business Systems Analysis

Question 3

0.1 / 0.1 pts

Consider the question: "how do I generate a monthly sales report?”. What type of user documentation can we find this information in?

Procedure manual

Question 4

0.1 / 0.1 pts

Reflect on the Cecil to Canvas conversion example discussed in class to answer this question. Which of the following strategies is true for the conversion from Cecil to Canvas.

Parallel, Pilot, Simultaneous, Whole system

Question 5

https://canvas.auckland.ac.nz/courses/62082/quizzes/65904

0.1 / 0.1 pts

3/7

5/29/2021

Quiz week 11: INFOSYS 220: Business Systems Analysis

As part of a comprehensive system migration plan, preparing the business involves ______________ and the other two aspects of the migration plan are _____________ and ______________.

Selecting a conversion strategy; Preparing the People; Preparing the Technology.

Question 6

0.1 / 0.1 pts

Which of the following conversion strategies pose the most risk

Direct, Simultaneous, Whole-system

https://canvas.auckland.ac.nz/courses/62082/quizzes/65904

4/7

5/29/2021

Incorrect

Quiz week 11: INFOSYS 220: Business Systems Analysis

0 / 0.1 pts

Question 7

Which one of the following options is an example of perfective maintenance?

A banking system is updated with new mortgage rates after the bank decides to offer a new mortgage product.

Question 8

0.1 / 0.1 pts

What is Agile development? [Select all appropriate options]

A category of iterative development approaches. https://canvas.auckland.ac.nz/courses/62082/quizzes/65904

5/7

5/29/2021

Quiz week 11: INFOSYS 220: Business Systems Analysis

A development method where requirements and solutions evolve through collaboration between self-organizing cross-functional teams.

Question 9

0.1 / 0.1 pts

Which of these are not typical of Agile development based on the Agile manifesto? [select all appropriate options]

A focus on the step by step actions to work through a solution.

Making sure that the terms and conditions, and contract for the project are dealt with foremost.

Question 10 https://canvas.auckland.ac.nz/courses/62082/quizzes/65904

0.1 / 0.1 pts

6/7

5/29/2021

Quiz week 11: INFOSYS 220: Business Systems Analysis

Which of the following systems need to prioritise "Availability" of information (CIA triad)?

A website hosting important information for the public