CSIS 3275 (Software Engineering) Exercises on Project Metrics Instructor: Victor Choong Answer the following question showing all workings for each question clearly. 1. Use the basic “Organic” COCOMO model to estimate the effort, development time, number of people required to develop the 6,450 lines of office automation system software. 2. Using the “semi-detached” COCOMO model, recalculated the figures in Question 1 3.

Assuming the labour rate for your company is $9,000 per person-month and your software project requires 18,000 LOC. Calculate the effort, development time and the cost of the project using the COCOMO Basic Model.

4. Assuming the average productivity is 7.5 FP/pm and the labour rate to be $10,000 per month. The estimated project requires 425 FPs. Calculate the following: a) The cost per function point b) The estimated project cost c) The estimated effort 5.

If the average productivity is now 6.3 FP/pm, recalculate the values in (a) to (c) in Question 4.

6. Based on the LOC approach, the company has a burden labour rate of $9,500 per month and the average productivity is 510 LOC/pm. The total LOC of the entire software project requires 40,528 lines of code. Calculate the following: a) Cost per line b) Project Cost c) Effort for the project

Victor Choong...