Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Test #3 Planning and Scheduling Due Sep 28 at 23:59

Points 20

Questions 20

Available Sep 25 at 0:00 - Sep 28 at 23:59 4 days

Time Limit 30 Minutes

Instrucons Read Chapter 9 Planning & Chapter 10 Scheduling Coordination of time, an essential function on every project.

Aempt History LATEST

Attempt

Time

Score

Attempt 1

24 minutes

11 out of 20

 Correct answers are hidden. Score for this quiz: 11 out of 20 Submitted Sep 28 at 0:17 This attempt took 24 minutes. Incorrect

Question 1

0 / 1 pts

The strategic plan is an essential first step in determining_

when to begin measurement.

https://swinburne.instructure.com/courses/24539/quizzes/96772

1/9

2020/9/27

Incorrect

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Question 2

0 / 1 pts

To enable bid prices to be compared on an "apples for apples" basis_

project engineers set the tenders up on a spreadsheet.

Incorrect

Question 3

0 / 1 pts

Planning should begin in the feasibility stages but be most intense_

during the tender stage.

Incorrect

Question 4

0 / 1 pts

Planning consists of logically assessing_

the time required to achieve a desired outcome.

https://swinburne.instructure.com/courses/24539/quizzes/96772

2/9

2020/9/27

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Question 5

1 / 1 pts

A Foreman does not work on the tools but a percentage of his/her time_

must be included in crew costs.

Question 6

1 / 1 pts

Planning involves forecasting the future and for that reason_

no plan will ever be exactly right.

Question 7

1 / 1 pts

Planning involves setting goals_

https://swinburne.instructure.com/courses/24539/quizzes/96772

3/9

2020/9/27

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

and formatting ways to reach those goals.

Incorrect

Question 8

0 / 1 pts

Planning must be closely associated with scheduling to_

be sure that the scheduler updates on a regular basis.

Incorrect

Question 9

0 / 1 pts

Once a project has been recognized as viable planning should be advanced at a rate_

to match the program to be developed by the project manager.

https://swinburne.instructure.com/courses/24539/quizzes/96772

4/9

2020/9/27

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Question 10

1 / 1 pts

In planning we need to be mindful of the Pareto Principle:

80% of the project cost will be in 20% of required work items.

Question 11

1 / 1 pts

The logic of activities in a project schedule should_

follow the sequence of the work.

Question 12

1 / 1 pts

During the project actual progress is monitored against the schedule, and_

any deviations are identified.

https://swinburne.instructure.com/courses/24539/quizzes/96772

5/9

2020/9/27

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Question 13

1 / 1 pts

Gantt charts, CPM programs, PERT and Line of Balance are_

all methods of displaying schedules.

Question 14

1 / 1 pts

Gantt charts, CPM programs, PERT and Line of Balance are_

all methods of displaying schedules.

Question 15

1 / 1 pts

Development of the Critical Path Method (CPM) is done_ https://swinburne.instructure.com/courses/24539/quizzes/96772

6/9

2020/9/27

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

in two steps, planning and scheduling.

Incorrect

Question 16

0 / 1 pts

Planning involves determining 'What', 'How' and 'Where to do it. Whereas_

Scheduling must have resource allocation for 'When' to do it.

Question 17

1 / 1 pts

The recommended approach to setting up a CPM schedule for a project is_

a planning step followed by a scheduling step.

https://swinburne.instructure.com/courses/24539/quizzes/96772

7/9

2020/9/27

Incorrect

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Question 18

0 / 1 pts

The Critical Path through schedule activities is

the shortest path.

Incorrect

Question 19

0 / 1 pts

In a successful project a well set up Work Breakdown Structure is_

helpful in arranging how the work will proceed.

Question 20

1 / 1 pts

Scheduling software uses equations to calculate_

early and late dates for the project.

https://swinburne.instructure.com/courses/24539/quizzes/96772

8/9

2020/9/27

Test #3 Planning and Scheduling: 2020-HS2-CVE30004-Cost Engineering

Quiz Score: 11 out of 20