Title | Varios p3-6b - practica A6 |
---|---|
Course | Contabilidad Analítica |
Institution | Universitat de Barcelona |
Pages | 16 |
File Size | 568.6 KB |
File Type | |
Total Downloads | 101 |
Total Views | 122 |
practica A6...
Do It! Review 16-1 Your answer is correct. Indicate whether each of the following statements is true or false. 1. Many hospitals use job order costing for small, routine medical procedures. False 2. A manufacturer of computer flash drives would use a job order cost system False 3. A process cost system uses multiple work in process accounts. True 4. A process cost system keeps track of costs on job cost sheets.
False
!
Question 8 Your answer is correct. Mark Haley is uncertain about the steps used to prepare a production cost report. State the procedures that are required in the sequence in which they are performed. (1)
Compute the physical unit flow.
(2)
Compute equivalent units of production.
(3)
Compute unit production costs.
(4)
Prepare a cost reconciliation schedule.
!
Question 14 Your answer is correct. Hindi Co. started 3,000 units during the period. Its beginning inventory is 500 units one-fourth complete as to conversion costs and 100% complete as to materials costs. Its ending inventory is 300 units one-fifth complete as to conversion costs and 100% complete as to materials costs. How many units were transferred out this period? Units transferred out 3200
!
Exercise 16-5 Your answer is correct. In Wayne Company, materials are entered at the beginning of each process. Work in process inventories, with the percentage of work done on conversion costs, and production data for its Sterilizing Department in selected months during 2014 are as follows. Beginning Work in Process Month
Units
Conversion Cost%
Ending Work in Process Units Transferred Out
Units
Conversion Cost%
January
0
—
9,000
2,000
60
March May
0 0
— —
12,000 16,000
3,000 7,000
30 80
July
0
—
10,000
1,500
40
(a) Compute the physical units for January and May. January Units to be accounted for Beginning work in process Started into production
May
11000
23000
Total units
11000
23000
Units accounted for Transferred out
9000
16000
Ending work in process Total units
2000
7000
11000
23000
(b) Compute the equivalent units of production for (1) materials and (2) conversion costs for each month.
January March
Materials Conversion Costs 11000 10200
May
15000 23000
12900 21600
July
11500
10600
!
Exercise 16-6 Your answer is correct. The Cutting Department of Cassel Company has the following production and cost data for July. Production
Costs
1.
Transferred out 12,000 units.
Beginning work in process
2.
Started 3,000 units that are 60%
Materials
45,000
$0
complete as to conversion
Labor
16,200
costs and 100% complete as
Manufacturing overhead
18,300
to materials at July 31. Materials are entered at the beginning of the process. Conversion costs are incurred uniformly during the process. (a) Determine the equivalent units of production for (1) materials and (2) conversion costs.
Total equivalent units of production
Materials Conversion Costs 15000 13800
(b) Compute unit costs. (Round unit costs to 2 decimal places, e.g. 2.25.) Materials
$3
Conversion costs $ 2.5 Prepare a cost reconciliation schedule. Cost Reconciliation Costs accounted for Transferred out
$ 66000
Work in process, July 31 Materials
$ 9000
Conversion costs
4500
Total costs
13500 $ 79500
!
Exercise 16-13 Your answer is correct. The Welding Department of Thorpe Company has the following production and manufacturing cost data for February 2014. All materials are added at the beginning of the process. Manufacturing Costs
Production Data
Beginning work in process Materials Conversion costs
$18,000 14,175
Materials
Beginning work in process
15,000 units, 1/10 comp
Units transferred out
49,000
$32,175
Units started
45,000
180,000
Ending work in process
11,000 units, 1/5 comple
Labor
52,380
Overhead
61,445
Prepare a production cost report for the Welding Department for the month of February. (Round unit costs to 2 decimal places, e.g. 2.25 and all other answers to 0 decimal places, e.g. 1,225.) THORPE MANUFACTURING COMPANY Welding Department Production Cost Report For the Month Ended February 28, 2014 Equivalent Units Physical Conversion Units Costs Quantities Materials Units to be accounted for Work in process, February 1 15000 Started into production
45000
Total units
60000
Units accounted for Transferred out
49000
49000
49000
11000
11000
2200
60000
60000
51200
Work in process, February 28 Total units Costs
Conversion
Unit costs Total Costs
Materials
Costs
$ 198000
$ 128000
60000
51200
$ 3.3
$ 2.5
Equivalent units Unit costs Costs to be accounted for Work in process, February 1
Total $ 326000 $ 5.8
$ 32,175 293825
Started into production Total costs
$ 326000
Cost Reconciliation Schedule Costs accounted for Transferred out Work in process, February 28 Materials
$ 284200 $ 36300
Conversion costs
5500
Total costs
41800 $ 326000
!
Exercise 16-15 Royale Mortgage Company uses a process cost system to accumulate costs in its loan application department. When an application is completed, it is forwarded to the loan department for final processing. The following processing and cost data pertain to September. 1. 2. 3. 4.
Applications in process on September 1, 100 Applications started in September, 900 Completed applications during September, 800 Applications still in process at September 30 were 100% complete as to materials (forms) and 60% complete as to conversion costs.
Beginning WIP: Direct materials
$1,000
Conversion costs
3,960
September costs: Direct materials
$4,500
Direct labor
12,000
Overhead
9,340
Materials are the forms used in the application process, and these costs are incurred at the beginning of the process. Conversion costs are incurred uniformly during the process. Your answer is correct. Determine the equivalent units of service (production) for materials and conversion costs.
The equivalent units of service (production)
Materials Conversion Costs 1000 920
Your answer is correct. Compute the unit cost. (Round unit costs to 2 decimal places, e.g. 2.25.)
Unit costs
Materials Conversion Costs $ 5.5 $ 27.50
Your answer is correct. Prepare a cost reconciliation schedule. Costs accounted for: Transferred out
$ 26400
Work in process, September 30 Materials
$ 1100
Conversion costs
3300
Total costs
4400 $ 30800
!
Exercise 16-3 The ledger of Custer Company has the following work in process account. Work in Process—Painting 5/1
Balance
3,590
5/31
Materials
5,160
5/31
Labor
2,740
5/31
Overhead
1,380
5/31
Balance
5/31 Transferred out
?
?
Production records show that there were 400 units in the beginning inventory, 30% complete, 1,400 units started, and 1,500 units transferred out. The beginning work in process had materials cost of $2,040 and conversion costs of $1,550. The units in ending inventory were 40% complete. Materials are entered at the beginning of the painting process. Your answer is correct. (a) How many units are in process at May 31? Work in process, May 31 300 units (b) What is the unit materials cost for May? (Round unit cost to 3 decimal places, e.g. 2.257.) The unit materials cost for May $ 4 (c) What is the unit conversion cost for May? (Round unit cost to 3 decimal places, e.g. 2.257.) The unit conversion cost for May $ 3.5 Your answer is correct. (a) What is the total cost of units transferred out in May? (Round answer to 0 decimal places, e.g. 1,225.) The total cost of units transferred out in May $ 11250
(b) What is the cost of the May 31 inventory? (Round answer to 0 decimal places, e.g. 1,225.) Work in process $ 1620
!
Problem 16-2A Rosenthal Company manufactures bowling balls through two processes: Molding and Packaging. In the Molding Department, the urethane, rubber, plastics, and other materials are molded into bowling balls. In the Packaging Department, the balls are placed in cartons and sent to the finished goods warehouse. All materials are entered at the beginning of each process. Labor and manufacturing overhead are incurred uniformly throughout each process. Production and cost data for the Molding Department during June 2014 are presented below. Production Data Beginning work in process units
June 0
Units started into production
22,000
Ending work in process units
2,000
Percent complete—ending inventory
40 %
Cost Data Materials
$ 198,000
Labor
53,600
Overhead
112,800
Total
$ 364,400
Your answer is correct. Prepare a schedule showing physical units of production. Physical units Units to be accounted for Work in process, June 1 Started into production
0 22000
Total units
22000
Units accounted for Transferred out
20000
Work in process, June 30 Total units
2000 22000
Your answer is correct. Determine the equivalent units of production for materials and conversion costs.
Total equivalent units
Materials Conversion Costs 22000 20800
Your answer is correct. Compute the unit costs of production. (Round unit costs to 2 decimal places, e.g. 2.25.)
Unit Costs
Materials Conversion Costs Total Unit Cost $9 $8 $ 17
Your answer is correct. Determine the costs to be assigned to the units transferred and in process for June. Transferred out
$ 340000
Work in process, June 30
$ 24400
Your answer is correct. Prepare a production cost report for the Molding Department for the month of June. ROSENTHAL COMPANY Molding Department Production Cost Report For the Month Ended June 30, 2014 Equivalent Units Physical Conversion Quantities Materials Units Costs Units to be accounted for Work in process, June 1 Started into production 22000 Total units
22000
Units accounted for Transferred out
20000
20000
20000
2000
2000
800
22000
22000
20800
Materials
Conversion Costs
Work in process, June 30 Total units
Costs Unit costs Total Costs Equivalent units Unit costs
$ 198000
$ 166400 $ 364400
22000
20800
$ 9
$ 8
Costs to be accounted for Work in process, June 1 Started into production
Conversion costs Total costs
$ 17
$ 364400
Total costs Cost Reconciliation Schedule Costs accounted for Transferred out Work in process, June 30 Materials
Total
$ 364400
$ 340000 $ 18000 6400
24400 $ 364400
!
Problem 16-3A Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production an cost data for the first process in making two products in two different manufacturing plants are as
follows. Cutting Department Plant 1 T12-Tables
Production Data—July Work in process units, July 1 Units started into production Work in process units, July 31
Plant 2 C10 -Chairs
0 19,000
0 16,000
3,000
500
60
80
Work in process percent complete Cost Data—July Work in process, July 1
$0
$0
Materials
380,000
288,000
Labor
234,200
110,000
Overhead
104,000
96,700
Total
$718,200
$494,700
Your answer is correct. For each plant: (1) Compute the physical units of production.
Units to be accounted for
T12 Tables C10 Chairs 19000 16000
(2) Compute equivalent units of production for materials and for conversion costs.
T12 Tables
Materials Conversion Costs 19000 17800
C10 Chairs
16000
15900
(3) Determine the unit costs of production. (Round unit costs to 0 decimal places, e.g. 25.)
Unit costs-T12 Tables
Materials Conversion Costs Total Costs $ 20 $ 19 $ 39
Unit costs-C10 Chairs
$ 18
$ 13
$ 31
(4) Show the assignment of costs to units transferred out and in process. T12 Tables Costs accounted for: Transferred out
$ 624000
Work in process Materials
$ 60000
Conversion costs
34200
Total costs C10 Chairs
94200 $ 718200
Costs accounted for: Transferred out
$ 480500
Work in process Materials Conversion costs
$ 9000 5200
Total costs
14200 $ 494700
Your answer is correct. Prepare the production cost report for Plant 1 for July 2014. SEAGREN INDUSTRIES INC. Cutting Department—Plant 1 Production Cost Report For the Month Ended July 31, 2014 Equivalent Units Physical Conversion Units Costs Materials Quantities Units to be accounted for Work in process, July 1 Started into production 19000 Total units
19000
Units accounted for Transferred out
16000
16000
16000
3000
3000
1800
19000
19000
17800
Materials
Conversion Costs
$ 380000
$ 338200
19000
17800
$ 20
$ 19
Work in process, July 31 Total units
Costs Unit costs Total Costs Equivalent units Unit costs Costs to be accounted for Work in process, July 1 Started into production
Conversion costs Total costs
!
Problem 16-5A
$ 718200 $ 39
$ 718200
Total costs Cost Reconciliation Schedule Costs accounted for Transferred out Work in process, July 31 Materials
Total
$ 718200
$ 624000 $ 60000 34200
94200 $ 718200
Morse Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of Jul 2014 are as follows.
Production Data—Basketballs Work in process units, July 1
Units 500
Units started into production
Percent Complete 60 %
1,250
Work in process units, July 31
600
40 %
Cost Data—Basketballs Work in process, July 1 Materials
$750
Conversion costs
600
$1,350
Direct materials
2,400
Direct labor
1,580
Manufacturing overhead
1,295
Your answer is correct. Calculate the following. (1) The equivalent units of production for materials and conversion costs.
Equivalent Units
Materials Conversion Costs 1750 1390
(2) The unit costs of production for materials and conversion costs. (Round unit costs to 3 decimal places, e.g. 2.257.)
Cost per unit
Materials Conversion Costs $ 1.8 $ 2.5
(3) The assignment of costs to units transferred out and in process at the end of the accounting period. (Round answers to 0 decimal places, e.g. 2,250.) Costs accounted for: Transferred out
$ 4945
Work in process, July 31 Materials Conversion costs Total costs
$ 1080 600
1680 $ 6625
Your answer is correct. Prepare a production cost report for the month of July for the basketballs. (Round unit costs to 3 decimal places, e.g. 2.257 and all other answers to 0 decimal places, e.g. 2,250.)
Quantities
MORSE COMPANY Basketball Department Production Cost Report For the Month Ended July 31, 2014 Equivalent Units Physical Conversion Materials Units Costs
Units to be accounted for Work in process, July 1
500
Started into production
1250
Total units
1750
Units accounted for Transferred out
1150
Work in process, July 31 Total units
Costs Unit costs Costs in July Equivalent units
1150
600
600
240
1750
1750
1390
Materials $ 3150
Unit costs
1150
Conversion Costs
Total
$ 3475 $ 6625
1750
1390
$ 1.8
$ 2.5
Costs to be accounted for Work in process, July 1
$ 4.3
$ 1350
Started into production
5275 $ 6625
Total costs Cost Reconciliation Schedule Costs accounted for Transferred out Work in process, July 31 Materials
$ 4945 $ 1080
Conversion costs
600
Total costs
1680 $ 6625
!
Problem 16-6A Hamilton Processing Company uses a weighted-average process cost system and manufactures a single product—a premium rug shampoo and cleaner. The manufacturing activity for the month of October has just been completed. A partially completed production cost report for the month of October for the mixing and cooking department is shown below. Your answer is correct. Prepare a schedule that shows how the equivalent units were compute...