DPP 2012 STANDAR SPESIFIKASI TEKNIS KONSTRUKSI JALAN REL, SIPIL, JEMBATAN DAN BANGUNAN KERETA API DIREKTORAT PRASARANA PERKERETAAPIAN DIREKTORAT JENDERAL PERKERETAAPIAN KEMENTERIAN PERHUBUNGAN DPP 2012 DAFTAR ISI BAB 1. UMUM S.1. Peraturan – Peraturan ...................................................


Description

DPP 2012

STANDAR SPESIFIKASI TEKNIS KONSTRUKSI JALAN REL, SIPIL, JEMBATAN DAN BANGUNAN KERETA API

DIREKTORAT PRASARANA PERKERETAAPIAN DIREKTORAT JENDERAL PERKERETAAPIAN KEMENTERIAN PERHUBUNGAN

DPP 2012

DAFTAR ISI BAB 1. UMUM S.1. S.2. S.3. S.4. S.5. S.6. S.7. S.8. S.9. S.10. S.11. S.12. S.13. S.14. S.15. S.16. S.17. S.18. S.19.

Peraturan – Peraturan ..................................................................................... U.1-1 Definisi ............................................................................................................ U.2-1 Mobilisasi dan Demobilisasi ............................................................................ U.3-1 Survei ............................................................................................................. U.4-1 Ruang kerja ..................................................................................................... U.5-1 Window Time .................................................................................................. U.6-1 Direksi Keet dan Gudang ............................................................................... U.7-1 Fasilitas Operasional Kerja.............................................................................. U.8-1 Pembersihan Lokasi Kerja ............................................................................... U.9-1 Kesehatan dan Keselamatan Kerja (K3) .......................................................... U.10-1 Dampak Lingkungan ....................................................................................... U.11-1 Jaminan dan Pengendalian Mutu .................................................................... U.12-1 Submittal ......................................................................................................... U.13-1 Pemeriksaan dan Pengujian ............................................................................ U.14-1 Organisasi Proyek ........................................................................................... U.15-1 Rapat Proyek .................................................................................................. U.16-1 Pelaporan ........................................................................................................ U.17-1 Serah Terima Pekerjaan.................................................................................. U.18-1 Masa Pemeliharaan ........................................................................................ U.19-1

BAB 2. SIPIL S.1. S.2. S.3. S.4. S.5. S.6. S.7. S.8. S.9. S.10. S.11. S.12. S.13. S.14. S.15. S.16. S.17. S.18. S.19. S.20.

Pekerjaan Pembongkaran ............................................................................... Pembersihan Lahan ....................................................................................... Galian Umum ................................................................................................. Galian pada Tanah Keras/Batuan .................................................................. Galian untuk Bangunan Struktur...................................................................... Timbunan dengan Material Tanah Pilihan ...................................................... Timbunan di Belakang Bangunan Struktur ..................................................... Timbunan dengan Material Berbutir................................................................. Perbaikan Tanah Dasar dengan Material berbutir dan Geotekstile .................. Pemasangan Geotekstile sebagai Separator................................................... Perbaikan Tanah Dasar dengan Kapur .......................................................... Dinding Penahan Tanah dengan Pasangan Batu Kali .................................... Dinding Penahan Tanah dengan Pasangan Beton Bertulang ......................... Dinding Penahan tanah dengan Pasangan Batu ............................................ Saluran Air Pracetak ...................................................................................... Pasangan Batu Kosong dan Bronjong ............................................................. Drainase Memanjang dan Melintang .............................................................. Gebalan Rumput ............................................................................................ Perlintasan Umum ........................................................................................... Pekerjaan Perkerasan Jalan ...........................................................................

S.1-1 S.2-1 S.3-1 S.4-1 S.5-1 S.6-1 S.7-1 S.8-1 S.9-1 S.10-1 S.11-1 S.12-1 S.13-1 S.14-1 S.15-1 S.16-1 S.17-1 S.18-1 S.19-1 S.20-1

DPP 2012 S.21. S.22.

Pekerjaan Pemagaran dengan Beton ............................................................. S.21-1 Pagar Besi Hias .............................................................................................. S.23-1

BAB 3. TRACK T.1. T.2. T.3. T.4. T.5. T.6. T.7. T.8. T.9. T.10. T.11. T.12. T.13. T.14. T.15. T.16. T.17. T.18.

Pengadaan Rel .............................................................................................. Pengadaan Wesel dan Pemasangan ............................................................. Pengadaan Sistem Penambat ........................................................................ Pengadaan Pelat Sambung ............................................................................ IRJ .................................................................................................................. Bantalan Beton dan Sistem Penambat ........................................................... Bantalan Kayu ................................................................................................ Pengadaan dan Pengelasan Rel .................................................................... Kompromis Rel ................................................................................................ Pengadaan Balas, Pengiriman dan Pengecekan ............................................ Pemasangan Track dan Pemecokan Awal ...................................................... Pemasangan Track pada Jembatan Tanpa Balas .......................................... Pengangkatan dan Listringan dan Pemecokan .............................................. Penggeseran Horisontal Track ....................................................................... Pekerjaan Bongkar Wesel .............................................................................. Blok Penahan (Sepur Badug) ......................................................................... Tamping dan Finishing dengan Mesin MTT .................................................... Pemasangan Rambu - Rambu .......................................................................

T.1-1 T.2-1 T.3-1 T.4-1 T.5-1 T.6-1 T.7-1 T.8-1 T.9-1 T.10-1 T.11-1 T.12-1 T.13-1 T.14-1 T.15-1 T.16-1 T.17-1 T.18-1

BAB 4. JEMBATAN DAN BOX CULVERT J.1. J.2. J.3. J.4. J.5. J.6. J.7. J.8. J.9. J.10. J.11. J.12.

Beton Struktur ................................................................................................. J.1-1 Beton Pratekan ............................................................................................... J.2-1 Baja Tulangan ................................................................................................. J.3-1 Baja Struktur ................................................................................................... J.4-1 Pelaksanaan Perakitan ................................................................................... J.5-1 Pondasi Tiang Bor (Bored Pile) ....................................................................... J.6-1 Tiang Pancang ................................................................................................ J.7-1 Struktur Pangkal dan Pilar ............................................................................... J.8-1 Andas Jembatan ............................................................................................. J.9-1 Railing Besi (Hand Rail) .................................................................................. J.10-1 Sheetpile Beton ............................................................................................... J.11-1 Sheetpile Baja ................................................................................................. J.12-1

BAB 5. BANGUNAN GEDUNG G.1. G.2. G.3. G.4. G.5. G.6. G.7.

Pekerjaan Pondasi .......................................................................................... Pekerjaan Konstruksi Baja .............................................................................. Pekerjaan Logam ............................................................................................ Pekerjaan Pasangan Batu - Bata .................................................................... Pekerjaan Plesteran/Acian Dinding ................................................................. Pekerjaan Dinding Keramik ............................................................................. Pekerjaan Alumunium Panel ...........................................................................

G.1-1 G.2-1 G.3-1 G.4-1 G.5-1 G.6-1 G.7-1

DPP 2012 G.8. G.9. G.10. G.11. G.12. G.13. G.14. G.15. G.16. G.17. G.18. G.19. G.20. G.21. G.22. G.23.

Pekerjaan Lantai Keramik ............................................................................... G.8-1 Pekerjaan Lantai Granite/Tile .......................................................................... G.9-1 Pekerjaan Paving Blok .................................................................................... G.10-1 Pekerjaan Water Proofing ............................................................................... G.11-1 Pekerjaan Kusen Aluminium ........................................................................... G.12-1 Pekerjaan Kayu ............................................................................................... G.13-1 Pekerjaan Kaca ............................................................................................... G.14-1 Pekerjaan Alat Penggantung dan Pengunci .................................................... G.15-1 Pekerjaan Langit-Langit Gypsum Board .......................................................... G.16-1 Pekerjaan Pengecatan .................................................................................... G.17-1 Pekerjaan Sanitair ........................................................................................... G.18-1 Pekerjaan Atap Lembaran Baja Gelombang .................................................... G.19-1 Pekerjaan Railing Besi .................................................................................... G.20-1 Pekerjaan Silicone Sealant .............................................................................. G.21-1 Pekerjaan Sistem Elektrikal ............................................................................. G.22-1 Pekerjaan Sistem Mekanikal ........................................................................... G.23-1

DPP 2012

BAB 1 UMUM

DPP 2012

U.1 PERATURAN – PERATURAN

1.

PERATURAN-PERATURAN YANG TERKAIT Dibawah ini adalah peraturan – peraturan yang dijadikan Pedoman dalam pelaksanaan pekerjaan dalam penyusunan spesifikasi teknis apabila terdapat perbedaan antara peraturan – peraturan dibawah ini dan spesifikasi teknis, maka yang berlaku adalah sesuai yang tercantum dalam spesifikasi teknis ini:           

Standar Nasional Indonesia (SNI) Peraturan Menteri Perhubungan No 28 Tahun 2011 tentang Persyaratan Teknis Jalur KA PD 10 (Peraturan Dinas) Hasil konsensus nasional rancangan SNI 1995, mengenai penambat elastis (clip, insulator, alas rel dan shoulder) Peraturan Beton Bertulang Indonesia 1971 Tata Cara Perhitungan Struktur Beton Untuk Bangunan Gedung (SKSNI T-151991-03); Peraturan Bahan Jalan Rel Indonesia (draft) Peraturan Pelaksanaan Pembangunan Jalan Rel (draft) Peraturan setempat yang berlaku Peraturan tenaga kerja/hukum perburuhan yang berlaku Peraturan-peraturan lain yang berlaku

Standard pelaksanaan yang dikeluarkan oleh industri-industri bahan bangunan yang dipakai di kegiatan ini.

U.1-1

DPP 2012

U.2 DEFINISI ISTILAH

DEFINISI

A AASHTO

: :

ACI ANSI ASTM

: : :

AREA

:

AWS BS JIS CBR UIC

: : : : :

SNI PBI Satker Konsultan Konsultan Perencana Konsultan MK Kontraktor HB

: : : : : : : :

Ampere American Association of State Highway and Transportation Officials American Concrete Institute American National Standard Institute American Society for Testing and Material American Railway Engineering Association American Welding Society `British Standards Japanese Industrial Standards California Bearing Ratio International Union of Railways Technical Specification Standar Nasional Indonesia Peraturan Beton Indonesia Satuan Kerja Penyedia Jasa Pengawasan Penyedia Jasa Perencanaan Penyedia Jasa Manajemen Konstruksi Penyedia Jasa Konstruksi Brinell Hardness

U.2-1

DPP 2012

U.3 MOBILISASI DAN DEMOBILISASI 1.

RUANG LINGKUP Pekerjaan ini meliputi pekerjaan pengiriman dan penarikan kembali semua sumber daya, tenaga kerja, bahan, peralatan, perlengkapan, dan lain lain untuk mendukung kegiatan pelaksanaan pekerjaan.

2.

MOBILISASI

2.1 Mobilisasi terdiri dari pekerjaan persiapan dan pelaksanaan, termasuk, tapi tidak terbatas pada kebutuhan-kebutuhan untuk mobilisasi personil, peralatan, pemasokan, dan suplemen lainnya yang diperlukan ke lokasi proyek, untuk pembangunan kantor, gudang dan fasilitas lainnya yang diperlukan untuk bekerja di proyek, dan untuk seluruh pekerjaan dan operasi lainnya yang harus dilakukan atau biaya yang diperlukan sebelum mulainya berbagai item pekerjaan kontrak di lokasi proyek.

2.2 Mobilisasi adalah pengiriman ke lokasi pekerjaan sumber daya yang dibutuhkan untuk pelaksanaan pekerjaan.

2.3 Mobilisasi dianggap selesai bila Kontraktor dapat melaksanakan dan diterima oleh Konsultan mengenai pemenuhan masing-masing persyaratan yang terkait yang disebutkan dalam kontrak. 3.

DEMOBILISASI

3.1 Demobilisasi mencakup penyiapan pengajuan yang diperlukan sebelum pengakhiran pekerjaan.Demobilisasi adalah penarikan kembali dari lokasi pekerjaan sumber daya yang dibutuhkan untuk pelaksanaan pekerjaan.

3.2 Demobilisasi akan dianggap selesai jika seluruh peralatan, bahan, personil, atau lainnya milik kontraktor telah dikeluarkan dari lokasi proyek, dan persyaratan – persyaratan penyelesaian pekerjaan sebagaimana diatur dalam kontrak telah terpenuhi.

U.3-1

DPP 2012

U.4 SURVEI

1.

RUANG LINGKUP Pekerjaan ini meliputi survei penelitian hasil desain konstruksi, survei topografi, survei utilitas, penyelidikan tanah, survei hidrologi dan hidrolika, dan lain - lain yang dibutuhkan untuk mendukung pelaksanaan pekerjaan.

2.

3.

SURVEI PENELITIAN HASIL DESAIN KONSTRUKSI 1)

Sebelum pekerjaan dimulai, Kontraktor wajib melakukan penelitian terhadap desain konstruksi yang terdapat dalam Kontrak.

2)

Bila terdapat hal-hal yang meragukan dalam desain konstruksi, Kontraktor harus berkoordinasi dengan Konsultan Perencana, Konnsultan dan PPK.

3)

Perbaikan terhadap desain (review design) diusulkan oleh Kontraktor kepada PPK untuk mendapat persetujuan.

SURVEI TOPOGRAFI 1) Kontraktor harus mengadakan pengukuran-pengukuran serta pemasangan patok-patok yang diperlukan untuk pekerjaan pembangunan dan bertanggung jawab penuh atas kebenaran dan ketepatan pengukuran tersebut sehingga dapat dijadikan benchmark sebagai titik acuan elevasi dan posisi bangunan. Patok-patok serta tanda patok harus dijaga sedemikian rupa sehingga kedudukannya tetap serta tidak terganggu selama pekerjaan berlangsung. 2) Kesalahan-kesalahan yang terjadi sebagai akibat kelalaian di dalam menentukan ukuran selama pelaksanaan menjadi tanggung jawab Kontraktor sepenuhnya. Oleh karena itu sebelum pelaksanaan dimulai Kontraktor diwajibkan mengadakan pemeriksaan menyeluruh terhadap gambar-gambar dan ketentuan yang ada.

4.

SURVEI UTILITAS 1) Kontraktor sebelum melaksanakan pekerjaan harus melakukan survei utilitas yang berada di lokasi pekerjaan. 2) Kontraktor sebelum melaksanakan pekerjaan harus berkoordinasi dengan PT.KAI untuk mengetahui kondisi utilitas yang ada di lokasi pekerjaan. 3) Hasil survei harus dibuat dokumentasi yang baik sebagai alat kerja.

U.4-1

DPP 2012 5.

PENYELIDIKAN TANAH 1) Kontraktor sebelum melaksanakan pekerjaan harus melakukan penelitian terhadap hasil penyelidikan tanah yang digunakan dalam proses desain. 2) Jika terdapat hal – hal yang belum diperhitungkan atau meragukan, Kontraktor dapat melakukan penyelidikan tanah tambahan. 3) Dalam melakukan penyelidikan tanah, Kontraktor harus mendapat persetujuan Konsultan dan PPK.

6.

SURVEI HIDROLOGI DAN HIDROLIKA Kontraktor harus melakukan survei hidrologi dan hidrolika untuk memastikan bahwa akibat yang ditimbulkan selama pelaksanaan pekerjaan tidak menimbulkan dampak negatif seperti banjir, penyumbatan, dan lain – lain.

U.4-2

DPP 2012

U.5 RUANG KERJA 1.

2.

3.

RUANG KERJA (RIGHT OF WAY) 1)

Ruang kerja akan menjadi lahan sementara atau permanen untuk melaksanakan pekerjaan. Konsultan harus menentukan lebar efektif dan batas-batas ruang kerja.

2)

Kontraktor harus memperhatikan ruang kerja sebagaimana ditetapkan oleh Konsultan.

3)

Kontraktor bertanggung jawab untuk menyediakan ruang kerja tambahan yang diperlukan untuk penyimpanan material, peralatan, dan lain – lain atas biaya sendiri.

PERIJINAN 1)

Setiap perijinan yang dibutuhkan untuk memindahkan material dan peralatan menjadi tanggung jawab Kontraktor.

2)

Kontraktor akan melakukan survei untuk mengetahui kondisi - kondisi dan kesulitan yang mungkin ditemui dalam pengangkutan material, pengangkutan peralatan, dan lain – lain.

3)

Kontraktor harus menentukan jalan akses untuk mengangkut material, peralatan, dan lain - lain.

PEMBERSIHAN LOKASI KERJA 1)

Wilayah kerja harus dipelihara secara tertib dan bebas dari hambatan untuk memberikan kondisi terbaik yang mungkin untuk berbagai operasi dan instalasi yang diperlukan.

2)

Limbah dan puing-puing harus dihilangkan dari lokasi kerja.

U.5-1

DPP 2012

U.6 WINDOW TIME

1.

RUANG LINGKUP Bagian ini mengatur penggunaan waktu untuk pelaksanaan pekerjaan terutama pekerjaan yang berpengaruh bagi operasi kereta api.

2.

3.

RENCANA KERJA PELAKSANAAN DI LAPANGAN 1)

Sebelum pelaksanaan pekerjaan, Kontraktor menyampaikan Rencana Kerja kepada Konsultan.

harus

menyiapkan

dan

2)

Didalam rencana kerja harus tercantum mengenai program keselamatan yang akan dilaksanakan oleh Kontraktor.

3)

Kontraktor dan PPK serta Konsultan harus berkoordinasi dengan PT.KAI sebelum melaksanakan pekerjaannya di track existing.

4)

Pelaksanaan pekerjaan yang terletak di lokasi ruang manfaat jalan KA harus berkoordinasi secara intensif kepada PT.KAI.

WINDOW TIME 1) Window Time adalah waktu yang digunakan diluar jam operasional kereta api. 2) Pekerjaan – pekerjaan yang telah diidentifikasi memerlukan ...