BSBINN601 Lead and Manage Organisational Change Assessment 1 Case Study Assessment 1 – Case Study
1. Identify the needs for strategic change through analysis of strategic plans contrasted with the practices as defined in the scenario. You may prefer to use SWOT analysis but this is optional. Business environment in recent years is highly competitive due to changing technology and changing customers’ sophistication. In order to maintain business growth and market interest, it is imperative for a business to analyse external forces and aligning the business objective to cope with the changes (Khan & Hashim, 2014). Meanwhile, some changes in organisation associate to improve current business operation in order to gain competitive advantages in its business environment (Teixeira & Werther, 2013). Based on the case study, Bounce Fitness experienced lack of standardisation in operations, due to that reason, the training sessions’ quality delivered deteriorated, thus resulting high customers’ dissatisfaction. Meanwhile, this issue caused Bounce Fitness unable to set systematic future planning for all centres as each centres made independent decision in operations. Due to all those reasons, it is crucial for Bounce Fitness to re-strategize the business operation to rectify problems associate to customers’ satisfaction. With strategic plan implemented, it may help Bounce Fitness to standardize its operation and build good national reputation as Fitness Australia provide high standard code of practice. Fitness Australia provide clear guideline on the method of training session being conducted(Fitness Australia, 2017).
2. Discuss any patterns or trends in the external environment which impact on the achievement of the organisations change management objectives. The fitness trends in Australia change dramatically over the years because people starting to pay attention to their health. This trends result fitness wearable tech sales to continue grow and predicted to worth at least $34 billion by 2020. Due to that reason, celebrity trainers’ marketing in Instagram attracted a lot of customers, however according to Berry (2016) mentioned that there are lot of celebrities training lack of professional training knowledge. Meanwhile, Schlossberg (2016) also stated the same problem of Instagram fitness trainers may have, these trainers lack of knowledge in proper training method may cause adverse effect to customers’ health. Even professional stated this problem may arise if approaching Instagram trainer but people still continue patronising these trainers. This marketing trend result organisation change management in acquiring professional training standard lack of important sense to some trainers who had high popularity.
3. Identify major operational change requirements due to performance gaps, business opportunities or threats, or management decisions for this change management initiative. The major operational change requirements required by Bounce Fitness at the moment is standardizing all its training activities corresponding to Fitness Australia’s code of practice. Furthermore, another issue regarding performance gaps was Bounce Fitness required to evaluate all employees’ professional knowledge, ensuring all trainers acquired the minimal requirements, Certificate III in Fitness. According
to Fitness Australia standard, Bounce Fitness’s trainers required to complete at least 20 CECs (Continuing Education Credit) every two years. Therefore, Bounce Fitness need to ensure all trainers of the centre to maintain such education needs. Main threat arising from this change was existing trainers without qualifications will resist change. In several cases, when change occurred, two type of forces appeared to reshape an organisation equilibrium, known as driving force and restraining force. Driving force was Bounce Fitness management and retraining force refers to the people affected by changes such as under-qualified trainers (Mersha, 1997). Due to that reason, it is highly important for Bounce Fitness management to persuade and establish an understanding with trainers who resist changes.
4. Discuss how you will review and prioritise change requirements/opportunities with relevant managers. Conduct web research and identify the name of an external specialist or expert who can help you identify major change requirements and opportunities in this case. Change management plan for Bounce Fitness consist three major part: 1.) restructuring decision making procedure, 2.) redesign training program align with Fitness Australia standard, and 3.) training and educate under qualified trainers. The main change requirement should be prioritised by Bounce Fitness was restructuring decision making procedures, rather than having each centres making decision autonomously, management should set a decision making protocol for all centre. With this change prioritised, Bounce Fitness can resolve the current managing problem due to lack of control, furthermore integrated overall development project and objectives set by headquarter. Follow by redesign training program so that Bounce Fitness can resolve problem associate to low customer satisfaction rate. As these changes take place, managers could attempt to discuss with under qualified trainers regarding the importance of going further education to cope with Bounce Fitness future planning. In change management, it often involve with redesign or reshaping existing organisation’s culture. According to Velasquez and Hussey (2013) stated that a successful organisation change highly associate to organisation culture management. In order to reshape current organisation’s culture to align with change requirements, Bounce Fitness may consider hiring an external consultant to assist on this matter. Based on web search, Culture Code Consulting firm located in Australia is highly reputable in helping Bounce Fitness to manage change. Dr. Timothy Foster was the lead consultant of Culture Code Consulting firm with former teaching qualification at Ridley College, Melbourne (Culture Code Consulting, 2017).
5. Complete a cost benefit analysis for high priority change requirements/opportunities. A cost benefit analysis (CBA) is a tool use to analyse the cost and benefit derive from change, it account both quality and quantitative measure of the project(The Economic Times, 2017).
Cost Benefit Analysis
Costs
Year
0
1
2
3
4
Centralised Management Software
4,000
500
500
500
500
Redesign Fitness Program
5,000
Trainers' Education & Training
8,000
1,000
1,000
1,000
1,000
Total Costs
17,000
1,500
1,500
1,500
1,500
Discount Factor (15% p.a.)
1.00
0.87
0.76
0.66
0.57
PV Cost
17,000
1,305
1,140
990
855
Cumulative PV Cost
17,000
18,305
19,445
20,435
21,290
500
500
500
500
500
New customers for fitness program
2,000
3,000
3,500
4,000
Increase customers due to professional trainers
1,500
1,500
2,000
2,500
Development costs
Benefits
Tangible Benefits from New Systems
Improve management and documentation
Intangible Benefits from New Systems
Improve decision making process
2,000
2,500
3,000
4,000
Higher company reputation
2,000
2,000
2,500
2,500
Higher customers' satisfaction
200
500
500
1,000
Total Benefits
500
8,200
10,000
12,000
14,500
Discount Factor (15% p.a.)
1.00
0.87
0.76
0.66
0.57
PV Benefits
500
7,134
7,600
7,920
8,265
Cumulative PV Benefits
500
7,634
15,234
23,154
31,419
Cumulative PV Benefits + Costs
- 16,500
- 10,671
- 4,211
2,719
10,129
6. Complete a risk analysis, identify barriers to change and agree and document mitigation strategies. Risk analysis table was used to identify and assess the possible risk that may occurred during implementation of change management. The risk will be rated based on likelihoods of occurring and the vulnerability of the consequences. The risks rating from 1 to 8 are consider low risk, 9 to 13 are consider average and 14 to 20 is high risk.
Consequences
Insignificant (1)
LikelihoodsAlmost
Minor
Moderate
Major
(2)
(3)
(4)
Catas
Certain (5)
Likely (4)
Redesign fitnessNew fitness programsManagers of each centre resist program conflicts not in demand central decision making
Possible (3)
Management softwareUnqualified breakdown resist training
trainers
Unlikely (2)
Rare (1)
Qualified trainers unwilling to participate education program
Mitigation strategy refers to the method of handling risk unacceptable by the management based on risk management analysis. Mitigation strategy aim was to minimise the impact of the risk or reducing the possibilities of occurring during implementation stage(Kossiakoff & Sweet, 2003). Several approaches can be used as mitigation strategy such as monetary incentives, coercive (punishment), promote collaboration through communication and gain understanding through joint discussion with all Bounce Fitness’s staff members.
7. From whom will you seek approval and confirm the change management process? In order to ensure change management process successfulness, it is necessary to present the implementation plan to all relevant personnel. First of all, the plan required external consultant to review all associate criterion to examine the feasibility of the plan. After gain approval from external consultant, the report will be presented to chief finance officer from finance department to examine the budget practicability. Next, the report will be present to chief executive officer to confirm and approve the implementation. The rationale behind these steps were to ensure the plan is effective and meet all financial commitments.
8. What resources will you need and how will you report to and gain information from relevant managers? During reporting and information gathering phase, two important criteria need to be taken into account; 1.) All relevant materials associate to changes must be present in the report and 2.) Promote participation and collaboration of manager through mutual understanding and tolerances. Relevant resources include performances analysis stating the progress of all fitness program development, sales data, customer complaint report, interval plan budget report and trainers’ education progress. These resources will be compiled into a major report for all managers, meanwhile during presentation period, a simplified power point presentation will be made so that managers could have quick review of all
New system
important data. In order gain feedback from managers, a questionnaire will be given to all managers to fill in the information they experiencing when they executing the plan. Aside that, an information sharing platform will be setup for managers to post and share information. Meanwhile, management may post updated data along implementation period to support managers’ effort in executing development project.
9. Develop a communication plan and discuss how you will consult with relevant groups and individuals. Do not forget that you must report to the Executive as well as communicate widely with Centre staff. In most cases, organisational change caused uncertainty and anxiousness to all employees (Velasquez & Hussey, 2013). This problem usually resulted from lack of communication between groups and individuals. Therefore keeping discussion focused, relevant and timely with regular meetings through multiple channels and media is important. Regular meetings can be in two form, casual gathering or formal meeting
such
as
daily
meeting, lunch
activities
and
monthly meeting. Meanwhile
communication channels can be in form of notice board, memos, emails, telecommunications, video conferencing, presentation and management software’s media. Aside that, the communication plan need to include all members associated to the development plan, this include external consultants.
10.Develop your communication/education plan to promote the benefits of the change to the organisation, and to minimise loss, and arrange activities to deliver the communication plan to all relevant groups and individuals. The communication plan aim to promote benefits of the change and minimise loss through acquiring change information from relevant group and individuals. In order to do so, several meetings method were designed to communicate with different audiences with different messages through appropriate media and channels. Kindly refer to the communication plan as following:
Communication Plan
Type
ofDescription
Schedule Audiences
Meeting
Briefing
Changes to be implemented and performances Weekly
Fitness Trainers / General Staff
of staffs
Formal
Delivered
Media / Channel
by
Report of progress, budget, and performances
Meeting
Monthly
Centre
Fitness Centre (Fa
Manager
Notice / Memo
Executive Management / StoreProject
Report / Meeting
Manager / External Consultant
Manager
Face) / Email all relat
Restaurant, Casual
Lunch
Sharing implementation experiences, discuss FortnightlyGeneral Staff / Store Manager
Project
Activities
new possible change to be implemented
Manager
Presentation
Result of implementation and data associated to Monthly
External Consultant / ExecutiveProject
Power Point / Meetin
changes
Management
Face)
Manager
11.How will you consult with relevant groups and individuals for input to the change process after the implementation commences? Consultation priority was to get continual feedback, evaluation, and possible solution from employees, representatives, committees, managers and individual staffs. Therefore it is highly important to identify the consultation function whether it is for informing, consulting or negotiating. During consultation process, it is necessary to explain the final decisions to the audiences if their views and opinions were not adopted. Meanwhile, give credit and recognition to those who provide information which used and improved a situation; and ensure the discussed issue are relevant to the plan. Aside that, it is highly important to avoid discussing minor issues that may cause grievances. Finally, presenters should always provide feedback to audiences on the development outcome as this may keep all members associated to changes notified and motivated.
12.What barriers to change do you see as possible? Develop a risk management and mitigation plan for each. In general, low risk threats that are unlikely to occur is less important, mitigation plan for the risk management will focus on moderate and high risk factors only. Therefore, the mitigation plan will list out a series of approaches to anticipate potential problems such as managers’ resistances, management software failure, new fitness program not in demand and unqualified trainers resistance on training participation.
13.In your change management plan, include action plans and activities and the project timetable. You may use a Critical Path Analysis or Gantt chart for this, but may choose to use another method. Actions
IT Activities
Responsible Person
Installing
management Software
Timeframe
1 week
software for joint decisionprogrammer making management
Installing new computers forTechnician all fitness centres
1 week
Design and setupSoftware communication platform forprogrammer
2 weeks
all staff members
Business Product Activities
/ Training Group managers
session
Unit
on
forManagement
softwareExecutives
function
Setup the budget for all plan Finance Officer
Conduct
Project Activities
1 week
market
1 week
trendRegional manager Throughout
analysis for designing new
implementing
fitness program
period
and Team Review development plan
Collect
feedback
finaliseProject manager
fromProject
the
1 month
2 weeks
employees regarding whatmanagement team Communication Setup Activities meeting
they expecting
routine Secretary standard
for employees Assess
Technician
Th im pe
7 days
communication tools
Training Activities Prepare
budget
and Store
manager
timetable for fitness trainers Project management team to go for education class
/1 month Audit PreparationSetup
monitoringStore managerTh
and evaluation / Projectim mechanism manager pe
Task
Description
Start Date
Duration
Dependent
Ty
Task 1
Situational analysis
1/07/17
7
Task 2
Consultation with all staff members
8/07/17
7
Task 1
Se
Task 3
Drafting change management report
15/07/17
7
Task 2
Se
Task 4
Create a financial budget
22/07/17
7
Task 3
Se
Task 5
Review draft report and finalise
22/07/17
7
Task 3
Pa
Task 6
Install management software
30/07/17
7
Task 5
Se
Task 7
Design and setup communication platform
30/07/17
14
Task 5
Se
Task 8
Installing new computers
6/08/17
7
Task 6
Pa
Task 9
Conduct trend analysis
30/07/17
28...