Task #1 Activity

Description

A B C D E F G H I J

Pour Foundation Erect Frame Roof Windows Door Electrical Rough-in-time Door Opener Paint Cleaning

Preceding Activity None A A A B,C C C,D E,F,G H I

Activity Time 3 Working Days 4 4 1 1 3 2 1 2 1

Project Network Diagram

A B

E

C

F

D

G

H

I

J

Forward & Backward Path

0 A 3 0 3 3

3 B 7 3 4 7

7 E 8 9 1 10

3 C 7 3 4 7

7 F 10 7 3 10

3 D 46 1 7 12 1 13

7 G 9 8 2 10

10 H 11 10 1 11

11 I 13 11 2 13

13 J 14 13 1 14

Critical Path Path Sequence :: A>> C >> F >> H >> I >>J (RED MARKED BELOW)

0 A 3 0 3 3

3 B 7 3 4 7

7 E 8 9 1 10

3 C 7 3 4 7

7 F 10 7 3 10

3 D 46 1 7 12 1 13

7 G 9 8 2 10

Project Duration :: 3+4+3+1+2+1 = 14 Days Total Float :: 3 Days ( FROM Forward & Backward Path)

10 H 11 10 1 11

11 I 13 11 2 13

13 J 14 13 1 14

Task # 2 Activity

Description

A B C D E F G H

Pour Foundation Erect Frame Roof Windows Door Electrical Rough-in-time Door Opener

Preceding Activity None A A B,C B D E,F G

Activity Time 5 Working Days 6 5 4 4 7 4 3

Project Network Diagram

A B

C

D

E

F

H

G

Forward & Backward Path

5 B 11 5 6 11

0 A 5 0 5 5

11 D 15 11 4 15

5 C 10 6 5 11

15 F 22 15 7 22

22 G 26 22 4 26

26 H 29 26 3 29

11 E 15 18 4 22

Critical Path Path Sequence :: A>> B >> D >> F >> G >>H (RED MARKED BELOW)

5 B 11 5 6 11

0 A 5 0 5 5

11 D 15 11 4 15

5 C 10 6 5 11

15 F 22 15 7 22

11 E 15 18 4 22

Project Duration :: 5+6+4+7+4+3 = 29 Days Total Float :: 7 Days ( FROM Forward & Backward Path)

22 G 26 22 4 26

26 H 29 26 3 29...