Task #1 Activity
Description
A B C D E F G H I J
Pour Foundation Erect Frame Roof Windows Door Electrical Rough-in-time Door Opener Paint Cleaning
Preceding Activity None A A A B,C C C,D E,F,G H I
Activity Time 3 Working Days 4 4 1 1 3 2 1 2 1
Project Network Diagram
A B
E
C
F
D
G
H
I
J
Forward & Backward Path
0 A 3 0 3 3
3 B 7 3 4 7
7 E 8 9 1 10
3 C 7 3 4 7
7 F 10 7 3 10
3 D 46 1 7 12 1 13
7 G 9 8 2 10
10 H 11 10 1 11
11 I 13 11 2 13
13 J 14 13 1 14
Critical Path Path Sequence :: A>> C >> F >> H >> I >>J (RED MARKED BELOW)
0 A 3 0 3 3
3 B 7 3 4 7
7 E 8 9 1 10
3 C 7 3 4 7
7 F 10 7 3 10
3 D 46 1 7 12 1 13
7 G 9 8 2 10
Project Duration :: 3+4+3+1+2+1 = 14 Days Total Float :: 3 Days ( FROM Forward & Backward Path)
10 H 11 10 1 11
11 I 13 11 2 13
13 J 14 13 1 14
Task # 2 Activity
Description
A B C D E F G H
Pour Foundation Erect Frame Roof Windows Door Electrical Rough-in-time Door Opener
Preceding Activity None A A B,C B D E,F G
Activity Time 5 Working Days 6 5 4 4 7 4 3
Project Network Diagram
A B
C
D
E
F
H
G
Forward & Backward Path
5 B 11 5 6 11
0 A 5 0 5 5
11 D 15 11 4 15
5 C 10 6 5 11
15 F 22 15 7 22
22 G 26 22 4 26
26 H 29 26 3 29
11 E 15 18 4 22
Critical Path Path Sequence :: A>> B >> D >> F >> G >>H (RED MARKED BELOW)
5 B 11 5 6 11
0 A 5 0 5 5
11 D 15 11 4 15
5 C 10 6 5 11
15 F 22 15 7 22
11 E 15 18 4 22
Project Duration :: 5+6+4+7+4+3 = 29 Days Total Float :: 7 Days ( FROM Forward & Backward Path)
22 G 26 22 4 26
26 H 29 26 3 29...