Title | Technical Report Engineering |
---|---|
Author | geoffrey nsubuga |
Course | Electrical Engineering |
Institution | Makerere University |
Pages | 140 |
File Size | 6.6 MB |
File Type | |
Total Downloads | 293 |
Total Views | 888 |
APPLICATION FOR MEMBERSHIP IN THE UGANDA INSTITUTION OF PROFESSIONAL ENGINEERS (UIPE) TO THE CLASS OF MEMBER AND REGISTRATION WITH ENGINEERS REGISTRATION BOARD (ERB) TECHNICAL REPORT ON DESIGN REVIEW OF SOROTI MOROTO LOT 1 AND LOT 2 (150) AND CONSTRUCTION SUPERVISION OF SOROTI MOROTO LOT 1 PROJECT (...
APPLICATION FOR MEMBERSHIP IN THE UGANDA INSTITUTION OF PROFESSIONAL ENGINEERS (UIPE) TO THE CLASS OF MEMBER AND REGISTRATION WITH ENGINEERS REGISTRATION BOARD (ERB)
TECHNICAL REPORT ON DESIGN REVIEW OF SOROTI – MOROTO LOT 1 AND LOT 2 (150.3KM) AND CONSTRUCTION SUPERVISION OF SOROTI – MOROTO LOT 1 PROJECT (100.0KM)
REPORT
SUBMITTED BY GEOFFREY NSUBUGA BSc Civil Engineering Email: [email protected] DECEMBER 2017
Technical Report
EXECUTIVE SUMMARY Uganda National Roads Authority (UNRA) is implementing An In-house supervision team to perform. I was deployed on the Upgrading of Soroti - Moroto Road in December 2016 to carryout Design Review and Construction supervision for Soroti – Akism and Akisim - Moroto as a Materials Engineer until procurement of the Supervision Consultant was completed. At the project start up brief, major challenges were identified like omission of swamp treatment by the design consultant, inadequate bridge foundation studies, Natural sands with high silt content and black cotton soils along most sections of the project. A design review was done to eliminate the challenges identified at the start-up of the construction process. Swamp treatment was determined using rock fill, Crushed Rock blinding and a geotextile membrane, crusher run sand was tested and conformed to sand requirements. The Alignment was resampled at intervals of 500m to identify soils unsuitable for road bed preparation as outlined in Clause…………. Additional boreholes were drilled at bridge locations to qualify foundation design parameters. The excavation method was adopted for swamp treatment, unsuitable black cotton soils replaced with a layer of G7 material and compacted to 95% MDD. The unit rates for swamp treatment components were established by the Applicant under the supervision of the Resident Engineer. Dynamic Cone Penetrometer and Dynamic Lightweight Penetrometer were performed by the Applicant to establish subsurface characteristics for pipe and box culverts respectively considering the depth under foundation influence. The applicant obtained control samples and instructed Field Density Tests on all constructed fill and pavement layers to establish conformance to the specifications. During Construction, field site trials were performed for subbase, base and surface dressing to establish performance and optimisation.
ii
Technical Report
DECLARATION I declare that the content presented in this technical report is a record of my active participation and involvement with significant degree of responsibility on the upgrading of Soroti - Moroto Road Project as a Materials and Pavement Engineer for the design review and construction supervision. The technical content is my interpretation and understanding of engineering facts.
........................................................................ Geoffrey Nsubuga Materials Engineer (UNRA)
iii
Technical Report
ACKNOWLEDGEMENT I express my sincere gratitude to the Directorate of Network Planning and Engineering for granting me an opportunity to work with the UNRA Construction and Supervision Team on the Construction Supervision of Soroti – Moroto Project Lot 1 and 2 as a Materials Engineer.
iv
Technical Report
TECHNICAL REPORT TABLE OF CONTENTS Chapter
Description
Page
EXECUTIVE SUMMARY
ii
1
BACKGROUND
1
1.1
Introduction
1
1.2
Introduction (THE PROJECT)
1
1.3
Background of the project
1
1.4
Civil Works Contract
1
1.5
Consultancy contract
2
1.6
Project location
2
1.7
Topography and Climate
3
1.8
The Project Organogram
3
MATERIALS INVESTIGATIONS
5
2.1
Subgrade soil investigations
5
2.2
Prospection for Construction Materials
6
2.3
Subbase Materials
8
2.4
Hard Rock
8
2.5
Water Sources
9
2.6
Sand
9
2.7
Swamps along the Project Route
10
2.8
Swamp Locations
10
2.9
Geotechnical Investigations along Swamps
11
2.10
Additional Swamp Investigations
11
2.11
Settlement Characteristics of the swamps
11
2.12
Swamp Treatment Method
12
2
v
Technical Report
3
2.13
Excavation method
12
2.14
Displacement Method
12
2.15
Quantity of Rock fill
13
2.16
Geotechnical investigations at bridge and major box culvert locations
13
2.17
Foundation Parameters
15
PAVEMENT EVALUATION
17
3.1
Subgrade Classification
17
3.2
Traffic Loading
18
3.3
Assessment of Past Traffic Estimates
18
3.4
Present traffic counts
18
3.5
AXLE LOAD DATA
20
3.6
Origin and Destination Surveys
23
3.7
TRAFFIC GROWTH RATES
23
3.8
Traffic forecast
25
3.9
Design Traffic Loading
25
3.10
PAVEMENT STRUCTURE
26
3.11
Design Consultant’s Proposed Pavement Structure
26
3.12
Revised Pavement Structure at Tender Stage
27
3.13
Pavement Design Review.
27
3.14
AASHTO DESIGN (Structural Number Method)
28
3.15
Proposed Pavement Structure
29
Figure 9: Urban Pavement Cross section
30
Figure 10: Urban Cross section
30
4
3.16
Surface Treatment
30
3.17
Chippings for Surface Dressing
31
3.18
Bitumen Specifications
31
3.19
Tests on Aggregates and Bitumen
31
SURFACE DRESSING DESIGN
32
4.1
Design of Spray rates
32
4.2
Design of Spread rates
34
vi
Technical Report 4.3 5
6
Prime Coat (MC30)
35
CONSTRUCTION SUPERVISION
36
5.1
Introduction
36
5.2
Drainage Inventory
36
5.3
Maintenance of the Existing Road
37
5.4
Site Clearance
37
5.5
Borrow pit Acquisition and Exploitation
38
5.6
Earth Works
38
5.7
Swamp Treatment
39
5.8
Quarry Rock and Operation
39
5.9
Concrete Production and Materials
40
5.10
Concrete Mix Designs
41
5.11
Culverts Crushing Test.
42
5.12
Tests on Bituminous Materials
43
5.13
MC-30 Cut back for Priming
45
5.14
Steel Reinforcement bars
45
5.15
Challenges encountered during Testing of Materials
45
5.16
Pavement layers of Natural gravel material
46
5.17
Stabilisation-Mechanical Modification (Subbase G 30)
46
5.18
Crushed Aggregate Road Base
48
5.19
Challenges for Earth Works and Pavement Layers Construction
48
5.20
Surface Dressing
48
5.21
Field trials for surface dressing
49
5.22
Field Observations
52
5.23
Traffic Management and Control
53
ENVIRONMENTAL MANAGEMENT
54
6.1
Introduction
54
6.2
Potential Impacts of the Project
54
6.3
Mitigation Measures
55
6.4
Monitoring and Supervision
55
vii
Technical Report 7
8
9
PROJECT RISK MANAGEMENT
56
7.1
Introduction
56
7.2
Risk Identification
56
7.3
Risk Assessment, Analysis and Mitigation Measures
56
CONCLUSION, RECOMMENDATIONS & CHALLENGES
62
8.1
Conclusions
62
8.2
Challenges
64
REFERENCES
66
APPENDICIES
67
viii
Technical Report
LIST OF FIGURES Description
Page
Figure 1: Project Location ....................................................................................................................... 3 Figure 2: Project Organogram ................................................................................................................ 4 Figure 3: Proposed 3 span bridge ......................................................................................................... 14 Figure 4: Proposed single span bridge ................................................................................................. 14 Figure 5: Classification of Predominant Clay Types ............................................................................. 15 Figure 6: Traffic Counts Stations ..........................................................................................................19 Figure 7: Axle Load Set up at Television ( Mbale - Soroti Road)......................................................... 21 Figure 8: Pavement Evaluation Soroti - Akisim(0+000 –150+300) Analysis 1 ..................................... 29 Figure 9: Urban Pavement Cross section ............................................................................................. 30 Figure 10: Urban Cross section ............................................................................................................ 30 Figure 11: Common Slump Forms ........................................................................................................ 41
ix
Technical Report
LIST OF TABLES Description Page Table 1: Sections with Unsuitable Soils for roadbed Preparation ............................... 5 Table 2: Borrow Pit Locations identified by Design Consultant .................................. 6 Table 3: Borrow Pit Locations and Materials Quality .................................................. 7 Table 4: Hard Rock Sources ...................................................................................... 8 Table 5: Chemical Test Results ................................................................................. 9 Table 6: Identified Sand Deposits ............................................................................ 10 Table 7: Summary of Swamp Details ....................................................................... 10 Table 8: Summary of Swamp Consolidation Parameters ......................................... 12 Table 9: Provisional Quantities of Rock fill ............................................................... 13 Table 10:Typical Properties of Clay Types ............................................................... 15 Table 11: Foundation Proposals .............................................................................. 17 Table 12: Summary of Classified Traffic Counts along the route (2010) in the most trafficked lane ........................................................................................................... 18 Table 13: Soroti - Moroto Directional ADT Traffic. .................................................... 19 Table 14: Moroto - Soroti Directional ADT Traffic ..................................................... 20 Table 15: Vehicle Equivalent Factors on projects with the area ............................... 22 Table 16: Traffic growth scenarios ........................................................................... 24 Table 17: Demand Elasticity of Petrol and Diesel .................................................... 24 Table 18: Pavement Design Life Selection............................................................... 25 Table 19:Summary of 15 Year Design Cumulative ESA’s........................................ 25 Table 20:Subgrade Classification ............................................................................. 27 Table 21: Proposed Pavement Structure ................................................................. 29 Table 22:Weighing factor for the 1st Seal chippings ................................................ 32 Table 23:Adjustment factors for spray rates (1st seal) ............................................. 33 Table 24:Weighing factor for the 2st Seal chippings ................................................ 33 Table 25:Adjustment factors for spray rates (2st seal) ............................................. 33 Table 26: Designed Spray and Spread rates for surface dressing ........................... 35 Table 27: Tests results for Cement. ......................................................................... 40 Table 28: Problems Encountered while testing materials ......................................... 46 Table 29: Proportions of G30 Material...................................................................... 46 Table 30:Labour mobilised for the trial Construction ................................................ 47 Table 31:Equipment at km 68+000 .......................................................................... 47 Table 32: Equipment at the borrow pit at km 68+300 RHS. ..................................... 47 Table 33: Challenges during the Construction of Earth Works and Pavement Layers ................................................................................................................................. 48 Table 34: Designed Spray and Spread rates for surface dressing ........................... 51 Table 35: Designed Spray and Spread rates for surface dressing ........................... 52 Table 36: Challenges encountered during surface dressing Construction ............... 52 Table 37: Challenges during the Construction of Earth Works and Pavement Layers ................................................................................................................................. 53 Table 38:Risk identification and analysis matrix ....................................................... 58 Table 39:Lessons Learned from Design Review and Supervision ........................... 62 Table 40: Challenges and Actions Taken on the Project. ......................................... 64 x
Technical Report
LIST OF ABBREVIATIONS UNRA : Uganda National Roads Authority MoWT : Ministry of Works and Transport ADT : Average Daily Traffic AADT : Average Annual Daily Traffic BC : Base Course CESAs : Cumulative Equivalent Standard Axles DBST/ DSBS :Double Bituminous Surface Treatment/Double Seal Bituminous Surfacing DCP : Dynamic Cone Penetration ESA : Equivalent Standard Axles ESAL : Equivalent Standard Axle Loads MoWHC : Ministry of Works, Housing and Communications ORN-31 : Overseas Road Note 31 UBOS : Uganda Bureau of Statistics DC : Design Consultant
xi
1
BACKGROUND
1.1
Introduction
This document is the applicant’s summarised technical report on design review of Soroti – Akisim (Lot 1) and Akisim – Moroto (Lot 2) and construction of Soroti – Akisim (Lot 1). This is presented to demonstrate the applicant’s technical and professional competence. The first four chapters have been prepared to highlight the Applicant’s contribution in the in the materials, pavement and Geotechnical design review of the project road. Chapters five, six and seven cover my experience during the ongoing construction of the Soroti – Akisim road project lot 1. 1.2
Introduction (THE PROJECT)
1.3
Background of the project
The Government of Uganda (GOU) earmarked funds for the National Roads Development and Maintenance Programme (NRDMP), and it intends to apply part of the funds towards payments under the contract for upgrading to bituminous standard of the Soroti – Moroto Road (150.3km) from Gravel to Paved (Bituminous) standard. The Soroti-Moroto road provides an important link in the national road network and contributes significantly to the economic prosperity of northeast region. The road upgrading will also assist the administrative and social coverage in the region, reduce vehicleoperating costs and improve social services and trading opportunities. The road has been regularly affected by the floods during spells of heavy rains due to the low-lying nature of the terrain and a series of seasonal and permanent swamps along the route. The road was a gravel road of class C, in a poor condition; the overall riding quality being rated as unsatisfactory on most of the road stretches. The project starts at Arapai (Teso College) to Nadunget (Moroto). The route traverses districts of Soroti, Amuria, Katakwi and Napak joining the completed Nakapiripit – Moroto road at Nadunget junction. 1.4
Civil Works Contract
Consequently, Uganda National Roads Authority (UNRA) acting on behalf of the GOU, awarded Contract No. UNRA/WORKS/2015-16/00002/002 for the upgrading of the Akisim Moroto Road lot 2 (50.3km) to China Railway No.3 Engineering Group and Contract No. UNRA/Works/2015-16/00002/001 for the upgrading of Soroti – Akisim Lot 1(100km) to China Communication Construction Company with a commencement date of 1st November 2016. The value of the Civil Works Contracts are as listed in the table below:
Section
Contractor
Lot 1 Lot 2
CCCC CR3
Contract Sum 348,000,000,000 248,069,399,126
Duration (Month) 36 30
Technical Report The contract payments are broken into 75% payable in USD and the remaining 25% in UGX. These project sums are inclusive of all the local taxes. This is a pre These are pre –financed contracts with the following conditions to be achieved in the first year of construction. Section Lot 1 Lot 2
Physical progress 30% 30%
Accumulated IPC sums USD 30,000,000 USD 16,000,000
The project road is an earth road to be upgraded to a class II Standard paved road comprising of a carriageway width of 7.00m and shoulder width of 1.5m. The carriageway and shoulders to have a double surface dressing. 1.5
Consultancy contract
There was a delay in the procurement of the Consultancy services for both lot 1 and 2. To keep in line with the intended ...