ASSIGNMENT FOR LEAN SIX SIGMA...
ARGON SPECIFIC ERROR REDUCTION PROJECT
Project Charter
Page 1 of 3
1. Purpose This document specifies the objectives and the team that are associated with the Six Sigma project Canucks Insurance Company 2. Charter Project title Argon Specific Error Reduction Project Project sponsor Rick Meyers, Vice President of Eastern region of CIC Project champion Linda McArther, Director of Corporate accounts Project team members (s) Akshay Desai, Six Sigma Green Belt Stephanie Roy, Financial analysist Emily Kirkland, Subject matter experts Ronnie Beaver, Subject matter experts Project problem statement Group Benefits(GB) Plan Setup Team of Canucks Insurance Company(CIC) is suffering from high volume of errors due to ARGON coding/data entry. For example, during April-June 2018 time period, the company suffered an ARGON error rate of 32.61% for Corporate clients, maximum between all other system specific errors. Project objective The goal is to reduce the ARGON error rate by at least 25% by end of Q3 of 2018. In scope To launch a DMAIC Six Sigma project to reduce number of errors. To do a root cause analysis of the existing problem.
Out of scope CIC employees are present globally and most of the subject matter experts (SME) work in a different time zone. An examination discloses that most of the errors are occurred at CIC’s Manila location by their employees. Six Sigma core squad is located in Kitchener, Ontario. Also, during the peak time, SMEs have very limited availability. CIC’s GB Plan setup team also has very limited Data available.
ARGON SPECIFIC ERROR REDUCTION PROJECT
Project Charter
Page 2 of 3
Project CTQ (also called project metric or Y) ARGON Error Rate (maximum acceptable value = 5%) Defect definition ARGON Error Rate should be higher than 5%. Benefits The company can reduce over $560,000 occurring due to the overtime. There will be lesser customer complaints, rework, over time and results into reduced Lead
Time.
New Corporate clients will have positive onboarding experience.
Required resources Efficient workplace Software (For Analysis) Funds Phase completion schedule DMAIC phase
Phase completion date
Define (includes as-is process mapping)
12th June, 2018
Measure
8th July, 2018
Analyze
10th August, 2018
Improve
1st September, 2018
Control
15th September, 2018
ARGON SPECIFIC ERROR REDUCTION PROJECT
Project Charter
Page 3 of 3
3. Revision history Version 1.0 2.0
4.Approvals Version 1.0 2.0
Date 1st June, 2018 5th June, 2018
Date 1st June, 2018 5th June, 2018
Author Akshay Desai
Section
Akshay Desai
Summary of changes Changes in Out of Scope N. A
Approval by Linda McArther
Six Sigma role Akshay Desai
Record Submitted
Linda McArther
Akshay Desai
Submitted...