FEU INSTITUTE OF TECHNOLOGYNSTP – CWTS UNITPROJECT WAITING SHEDA proposed project for the construction of waiting sheds for Barangay Sta. RitabyMA. YSABELLA S. SEDIARIN2020112084-ASubmitted to:MR. ADRIAN DUQUEOCTOBER 24, 2020TABLE OF CONTENTS I. PROJECT SUMMARY II. COMMUNITY BACKGROUND III. STATEMEN...
FEU INSTITUTE OF TECHNOLOGY NSTP – CWTS UNIT PROJECT WAITING SHED A proposed project for the construction of waiting sheds for Barangay Sta. Rita
by
MA. YSABELLA S. SEDIARIN 202011208 4-A
Submitted to:
MR. ADRIAN DUQUE
OCTOBER 24, 2020
TABLE OF CONTENTS
I.
PROJECT SUMMARY ……………………………………………….
3
II.
COMMUNITY BACKGROUND …………………………………….
4
III.
STATEMENT OF NEED ……………………………………………..
5-6
IV.
GOAL …………………………………………………………………
7
V.
OBJECTIVES …………………………………………………………
7
VI.
TARGET RECIPIENTS ……………………………………………….
7
VII.
PROGRAM STEPS / MECHANICS…………………………………...
8-10
VIII.
ANNEX BARANGAY STA. RITA ON GOOGLE MAPS ……………………..
11
SAMPLE WAITING SHED DESIGN…………………………………
12
OVERALL BUDGET DOCUMENTWITHBREAKDOWN……………………………………
13-14
AREA CONTACT PERSONS AND CONTACT NUMBERS ………..
15
2
I.
PROJECT SUMMARY In 2015, a road-widening was started in Zambales. It was a project of the government
with the aim to provide the people a better traffic and safer road. But on the other side, it has a negative impact for the people of Zambales, especially to those barangays whose roads were widened first. Just like in Barangay Sta. Rita, a barangay located in the municipality of Cabangan. For the reason that included in the road-widening was the removal of most of the barangay’s waiting sheds and other people’s properties, the barangay people are only left with one functional waiting shed. Families whose houses were affected by the road-widening recovered easily from the changes in their homes, and instantly found solutions to repair their properties that were damaged. However, the waiting sheds that were destroyed, were not replaced until now since the day it was removed. As a result, the citizens of every barangays affected, just like in Barangay Sta. Rita, are experiencing difficulties in commuting. In this project, the building of waiting sheds in the selected areas of Barangay Sta. Rita are being proposed. With its goal of raising awareness in providing safety needs for the Barangay Sta. Rita people, as they wait for public transportation like buses, jeepneys, tricycles, and express vehicles. Another, under this project proposal is its objectives states that by the end of this year, the proposed waiting sheds will be accomplished and be ready for the usage of its target recipients, which are the residents and non-residents of Barangay Sta. Rita.
3
II.
COMMUNITY BACKGROUND Sta. Rita is a barangay located in the municipality of Cabangan, province of Zambales. This barangay shares its common borders with Barangay San Rafael, Barangay Apo-apo, Barangay San Antonio and Barangay Dolores that all can be found beside the national highway. With its wide area, it was divided by parts that results for it to have five districts/zones. This is the reason why people there are classified according to their location that is divided by what they call “Puroks”. The Purok 1 in the inner part of the barangay, Purok 2, 3, and 4 that can be seen beside the main roads, and the Purok 4 that is near the mountains. As a result, the total of the population of the barangay, when citizens from those five divisions are added is equal to 2,198 in number. Aside from having a lot of citizen than the other near barangays, Barangay Sta. Rita also has a lot of establishments in its area and can also be considered as one of the busiest Barangay in its town. People can find different kind of small eateries, basketball courts, multi-purpose halls, and other small businesses within its zone. In addition, public elementary and high schools are also located here, that’s the reason why there are always many people found in the streets every lunch time and afternoon, especially before the pandemic.
4
III.
STATEMENT OF NEED In 2015, a road-widening was started in Zambales. It was a project of the government with the aim to provide the people a better traffic and safer road. It is also for the tourists so that they will have a good impression and easier travel to the province, as the tourism industry in Zambales continuously rising. But it has a negative impact for the people of Zambales, especially to those barangays whose roads were widened first, as well as the houses that lies on it. For the reason that included in the road-widening was the removal of some part of their houses, and the barangay’s waiting sheds, to give way for the government’s project. Families whose houses were affected by the road-widening recovered easily from the changes in their homes, and instantly found solutions to repair their properties that were damaged. However, the waiting sheds that were destroyed, was not replaced until now since the day it was removed. As a result, the citizens of every barangays affected, just like in Barangay Sta. Rita, are experiencing difficulties in commuting. Others may not notice it, but the barangay having only one functional waiting shed makes it hard for its people, especially to those who doesn’t have private vehicles, and just depends on public transportation on their daily commute. This is the reason why it is really important to build a new set of waiting sheds in the area because of the fact that the waiting sheds, the small structures usually built alongside roads, serves as people’s waiting area as they wait for their rides. Also, it also provides shelter for the commuters against the hotness of the sun or from the rain when there’s a typhoon. In addition, having not enough available waiting sheds in the Barangay Sta. Rita, or even in another places, can be a hassle to people. They still have to look for alternative places where they can wait or find a shelter. Another, it can also be dangerous
5
for them especially when their alternatives are not safe and are prone to accidents. Due to this, it is really necessary to provide the people of Barangay Sta. Rita, as well as the nonresidents, the waiting sheds in different parts of the barangay. Even just the simpler ones, like the Sample Waiting Shed that I put in the Annex. It may not be as exceptional like others, but what important is, it can provide the real purpose of a waiting shed, which is to provide safety and shelter for people.
6
IV.
GOAL To raise awareness in providing safety needs for the residents and non-residents of
Barangay Sta. Rita, as they wait for public transportation like buses, jeepneys, tricycles, and express vehicles.
V.
OBJECTIVES At the end of the three – month preparation and construction of the waiting sheds, within the month of November and December, and as the year ends, the team will be able to provide the residents or non-residents of Barangay Sta. Rita enough waiting sheds where they can safely wait for public transportation.
VI.
TARGET RECIPIENTS The building of waiting sheds in the Barangay Sta. Rita will be beneficial to the barangay people. Waiting shed that will be built in selected areas of Barangay Sta. Rita will serve as the people’s safety and shelter provider as they wait for public vehicles. Whether they are just waiting for a tricycle so they can go in another barangay, a jeep to have a ride going to the other town, or a bus for a long-travel journey. Aside from them, it will also be useful for people who visits the barangay and for those who work in that area.
7
VII.
Activities
PROGRAM STEPS
Expected Output
Persons
Time Frame
Resource Needed
Responsible Planning
Introduced the proposed project and the purpose of it.
Lemon Group (the team)
First week of September
Place to conduct the presentation.
Barangay Officials Presented the waiting shed design made with the partner company (Headstone Builders and Construction Supply) to the Barangay for approval.
Lemon Group (the team)
The project proposal
September 10
Equipment needed for the presentation. Three hard – copies of project proposal. Powerpoint presentation of project proposal.
Headstone Builders and Construction Supply team Barangay Officials
Gathered information for the costings of materials and other expenses needed
Lemon Group (the team) Headstone Builders and Construction Supply team Barangay Officials
September 17 – September 25
List of prices of materials needed in the construction of waiting sheds. Additional information regarding to the project’s other expenses, such as the Labor of the workers.
8
Found the right spots where to build the waiting sheds
Lemon Group (the team)
September 26 – October 1
Headstone Builders and Construction Supply team
Finalized the project plan with the Barangay officials and the partner company
Barangay Officials Lemon Group members (the team)
An actual map of Barangay Sta. Rita where it clearly shows the details of every part of the whole barangay area. Or it can also be, an actual visit to the barangay area.
October 4 – October 10
Three hard copies of the finalized project plan. Powerpoint presentation of the finalized project plan,
Headstone Builders and Construction Supply team Barangay Officials Execution Started the project work.
Lemon Group members (the team)
October 20 – December 20
Headstone Builders and Construction Supply team Monitored progress and control changes
Engr. Harry Styles
Materials, equipment, and other things needed in building the waiting sheds. Manpower.
October 21 – December 20
An actual visit to the construction sites.
Engr. Louis Tomlinson
9
Lemon Group members Closure
Documented the project’s progress and outcomes.
Close the project.
Lemon Group members
Lemon Group members (the team)
October 21 – December 20
Camera for documentation.
December 22
Notebook and ballpen for notes taking. Project Analysis Project Report
Headstone Builders and Construction Supply team
10
BARANGAY STA. RITA ON GOOGLE MAPS
Reference: Google Maps
11
SAMPLE WAITING SHED DESIGN
Reference: https://www.pinterest.ph/pin/855261785462479500/
12
OVERALL BUDGET DOCUMENT WITH BREAKDOWN (Good for one unit waiting shed) PROJECT: LOCATION: CONTRACTOR: SUPPLY
CONSTRUCTION OF 1 UNIT WAITING SHED BRGY. STA. RITA CABANGAN ZAMBALES HEADSTONE BUILDERS AND CONSTRUCTION
SUBJECT: ESTIMATED FLOOR AREA:
BILLS OF MATERIALS 10 sqm.
S.N.
1
2
Item / Description
Qty.
Unit
Site Preparation
10
sqm.
Site Clearing and Layout
10
sqm.
10
Materials
Labor
Direct Cost UnitCost Unit Cost Amount Amount (Php)
SITE-WORKS
1,000
1,300
2,300
cu.m.
5,000
5,000
1
cu.m.
1,000
1,000
Steel Column 3" GI Pipe Sched 40 Steel Bench 2.5" GI Pipe Sched 40
14
lm
3,560
10,680
850
2,250
12,930
8
lm
1,890
2,835
850
1,800
4,635
Steel Trusses 1.5" GI Pipe Sched 20
20
lm
950
3,800
1,300
5,200
9,000
GI Tubular 1 1/4 x 1 1/4 x 1.5 mm thick
25
lm
475
2,850
850
2,250
MASONRY/CONCRETE WORKS Concrete Floor
Concrete Foundation 3 METAL/WELDING WORKS
5,100
13
4
ROOFING Curved Metal Roof
5
18
lm
2
sqm.
365
7,110
1,300
2,600
9,710
500
500
1,000
1,500
PAINTING
Painting Works
TOTAL COST
Prepared By: Engr. Harry Styles
51,175
Approved By: Kap. Joseph D. Ablola
14
AREA CONTACT PERSONS AND CONTACT NUMBERS
REPUBLIC OF THE PHILIPPINES PROVINCE OF ZAMBALES MUNICIPALITY OF CABANGAN BARANGAY STA. RITA OFFICIALS C.Y. 2018-2020
NAME
COMMITTEE
CONTACT NUMBER
Joseph D. Ablola
Barangay Captain
09997585201
Freddie M. Daniel
Infrastructure
09129124250
Roel D. Danila
Agriculture, Fisheries and Livelihood
09199480042
Amado D. Dagun
Health and Social Services
09389226499
Alexander D. Daco
Trade, Commerce, Industry, Tourism
09498751183
and Culture Danilo C. Santos
Finance/Appropriations
09109392002
Rogy R. Dabay
Education, Family Matters and
09489386190
Women George D. Dahipon
Peace and Order
09217285307
Venice C. Fontillas
Barangay Secretary
09127214960
Amelia A. Adoremos
Barangay Treasurer
09072782637
15...